DPWH Camarines Sur 3rd DEO
DPWH implementing office 7edf01a5ce04f33a8f58
Overview
DPWH contracts
869
Total listed value
₱11.52B
Distinct contractors
130
More info
Largest contractors
PRECIOUS CONSTRUCTION₱547.2M
The largest contractor holds 16.0% of this office's listed value.
Latest 25 from a total of 869 records
| Contract ID | Start | Description | Status | Contractor | Amount |
|---|---|---|---|---|---|
| 24FF0061 | 2 yrs 6 mo ago | CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT),BRGY GUINABAN OCAMPO CAMARINES SURBuildings and Facilities | Completed | PHIL MANNA CONSTRUCTION AND SUPPLY | ₱4.9M |
| 24FF0051 | 2 yrs 6 mo ago | CONSTRUCTION OF MULTI PURPOSE BUILDING (PANICUASON ELEM. SCHOOL) PANICUASON NAGA CITY CAMARINES SURBuildings and Facilities | Completed | PHIL MANNA CONSTRUCTION AND SUPPLY | ₱4.9M |
| 24FF0056 | 2 yrs 6 mo ago | BIP;ACCESS ROADS & /OR BRIDGES FROM THE NATIONAL ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF ROAD BRGY. CARANGCANG MAGARAO-BRGY SAN FRANCISCO BOMBON CAMARINES SURRoads | Completed | LAHDETH CONSTRUCTION AND SUPPLY | ₱4.8M |
| 24FF0064 | 2 yrs 6 mo ago | BIP;PUBLIC WATER SUPPLY SYSTEM-CONST. OF PUBLIC WATER SUPPLY SYSTEM(WATER SUPPLY/SEPTAGE & SEWERAGE-RAINWATER COLLECTORS) CAWADI, BRGY. PAOLBO CALABANGA CAMARINES SURGAA 2024 SSP | Completed | PHIL MANNA CONSTRUCTION AND SUPPLY | ₱9.6M |
| 24FF0055 | 2 yrs 6 mo ago | CONST. OF MULTI PURPOSE BUILDING,BUREAU OF JAIL MANAGEMENT & PENOLOGY NAGA CITY CAMARINES SURBuildings and Facilities | Completed | PHIL MANNA CONSTRUCTION AND SUPPLY | ₱4.9M |
| 24FF0059 | 2 yrs 6 mo ago | BIP;FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDING-FACILITIES-CONST. OF FLOOD MITIGATION STRUCTURE (DRAINAGE),JULIAN MELITON ELEM SCHOOL, CONCEPCION PEQUENA NAGA CITY CAMARINES SURFlood Control and Drainage | Completed | AA PAHATI CONSTRUCTION AND SUPPLY | ₱4.9M |
| 24FF0052 | 2 yrs 6 mo ago | BIP;ACCESS ROADS &/OR BRIDGES FROM THE NATL. ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES CONST. OF ACCESS ROAD, BRGY. PINIT OCAMPO CAMARINES SURRoads | Completed | PHIL MANNA CONSTRUCTION AND SUPPLY | ₱7.7M |
| 24FF0038 | 2 yrs 6 mo ago | BIP;FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-CONST, OF FLOOD MITIGATION STRUCTURE,BRGY. SAN AGUSTIN PILI CAMARINES SURGAA 2024 SSP | Completed | MEGA-ANT BUILDERS AND CONSTRUCTION SUPPLIES | ₱4.9M |
| 24FF0047 | 2 yrs 6 mo ago | 001;ASSET PRESERVATION PROG.-REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS-MANGUIRING-TOMAGODTOD-SIBOBO ROAD-K0458+000-KO458+126.8,KO458+256.5-KO459+430 ,KO463+187-KO464+267 CALABANGA CAMARINES SURGAA 2024 OO-1 | Completed | MEGA-ANT BUILDERS AND CONSTRUCTION SUPPLIES (52876) / STEVEN CONSTRUCTION & SUPPLY | ₱88.8M |
| 24FF0048 | 2 yrs 6 mo ago | 001;NETWORK DEVELEOPMENT PROGRAM-CONST. OF BY PASS & DIVERSION ROAD - CONST. OF BYPASS AND DIVERSION ROAD AT JUNCTION DAANG MAHARLIKA DEL ROSARIO- CARARAYAN -SAN ISIDRO-NRJ CAROLINA BY PASS ROAD BARANGAY DEL ROSARIO NAGA CITY CAMARINES SURGAA 2024 OO-1 | Completed | MEGA-ANT BUILDERS AND CONSTRUCTION SUPPLIES | ₱9.7M |
| 24FF0041 | 2 yrs 7 mo ago | 002; CONST/MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM-CONST. OF FLOOD MITIGATION STRUCTURE AT BGY. DOMINOROG CALABANGA CAMARINES SURFlood Control and Drainage | Completed | CENTERWAYS CONSTRUCTION AND DEVELOPMENT INC. | ₱96.3M |
| 24FF0043 | 2 yrs 7 mo ago | 002;CONST./MAINT. OF FLOOD MITIGATION STRUCTURE & DRAINAGE SYSTEM-CONST. OF FLOOD MITIGATION STRUCTURE,BRGY. CONCEPCION PEQUENA,NAGA CITY CAMARINES SURGAA 2024 OO-2 | Completed | PHILWORKS CONSTRUCTION AND SUPPLY | ₱143.2M |
| 24FF0044 | 2 yrs 7 mo ago | 002; CONST./MAINT. OF FLOOD MITIGATION STRUCTURE & DRAINAGE SYSTEM-CONST. OF FLOOD MITIGATION STRUCTURE, BGRY. TRIANGULO & BRGY. TABUCO NAGA CITY CAMARINES SURFlood Control and Drainage | Completed | PHILWORKS CONSTRUCTION AND SUPPLY | ₱143.2M |
| 24FF0045 | 2 yrs 7 mo ago | 002;CONST. /MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM-CONST. OF FLOOD MITIGATION STRUCTURE AT BRGY. SAN BERNARDINO CALABANGA CAMARINES SURGAA 2024 OO-2 | Completed | KCS CONSTRUCTION AND SUPPLY | ₱95.5M |
| 24FF0009 | 2 yrs 7 mo ago | BIP;ACCESS ROAD & OR BRIDGES FROM THE NATIONAL ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-CONST OF ACCESS ROAD BRGY SABANG CALABANGA CAMARINES SURRoads | Completed | AJFT CONSTRUCTION AND SUPPLIES | ₱4.9M |
| 24FF0035 | 2 yrs 7 mo ago | BIP;FLOOD MITIGATION STRUCTURES PROTECTING MAJOR /STRATEGIC PUBLIC BUILDING/FACILITIES-CONST. OF FLOOD MITIGATION STRUCTURE(SPILLWAY) BRGY. TINANGIS PILI CAMARINES SURFlood Control and Drainage | Completed | MEGA-ANT BUILDERS AND CONSTRUCTION SUPPLIES | ₱9.7M |
| 24FF0039 | 2 yrs 7 mo ago | 001;ASSET PRESERVATION PROG.-PREVENTIVE MAINT.-SECONDARY ROADS-PILI TIGAON -ALBAY BOUNDARY ROAD-KO457+000-KO457+054,KO457+085-KO459+323,KO459+355.13-KO460+095.40 OCAMPO CAMARINES SURRoads | Completed | NFH CONSTRUCTION & SUPPLY | ₱58.3M |
| 24FF0040 | 2 yrs 7 mo ago | SIPAG-ACCESS ROAD &-OR BRIDGES FROM THE NATL. ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BLDG./FACILITIES-RETROFITTING/STRENGHTENING OF PERMANENT BRIDGES ALONG NATIONAL ROAD,PILI DIVERSION BRIDGE III ALONG PILI DIVERSION RD.PILI CAM. SURBridges | Completed | DSB CONSTRUCTION & SUPPLY, INC. (FORMERLY: DSB CO (16126) / STEVEN CONSTRUCTION & SUPPLY | ₱57.9M |
| 24FF0042 | 2 yrs 7 mo ago | 002;CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS-CONST. OF FLOOD MITIGATION STRUCTURE,BICOL RIVER FLOOD CONTROL,BRGY. MABOLO NAGA CITY CAMARINES SURGAA 2024 OO-2 | Completed | PHILWORKS CONSTRUCTION AND SUPPLY | ₱138.7M |
| 24FF0032 | 2 yrs 7 mo ago | CONSTRUCTION OF EVACUATION CENTER,BRGY. IQUIN CANAMAN CAMARINES SURBuildings and Facilities | Completed | VIRGO CONSTRUCTION | ₱4.9M |
| 24FF0033 | 2 yrs 7 mo ago | CONSTRUCTION OF MULTI PURPOSE BUILDING(COVERED COURT) JOSE C. PREVOSA SR. HIGH SCHOOL ) FORMERLY UNION NATIONAL HIGH SCHOOL) BRGY. STO DOMINGO CALABANGA CAMARINES SURGAA 2024 SSP | Completed | PHIL MANNA CONSTRUCTION AND SUPPLY | ₱4.9M |
| 24FF0036 | 2 yrs 7 mo ago | 001;NETWORK DEVELOPMENT PROG.-ROAD WIDENING-TERTIARY ROADS-NAGA CAROLINA-PANICUASON RD.-KO442+371-KO442+787 NAGA CITY CAMARINES SURGAA 2024 OO-1 | On-Going | PEU CONSTRUCTION AND SUPPLY | ₱39.4M |
| 24FF0037 | 2 yrs 7 mo ago | 001;NETWORK DEVELOPMENT PROGRAM;ROAD WIDENING-SECONDARY ROAD-PILI TIGAON-ALBAY-BDRY. ROAD-K0455+627.40-KO457+054,KO457+085-KO457+641.40 PILI CAMARINES SURRoads | Completed | PHILWORKS CONSTRUCTION AND SUPPLY | ₱71.2M |
| 24FF0031 | 2 yrs 7 mo ago | CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT) BARANGAY TABUCO NAGA CITY CAMARINES SURGAA 2024 SSP | Completed | CISCO KVF CONSTRUCTION | ₱4.9M |
| 24FF0034 | 2 yrs 7 mo ago | CONSTRUCTION OF MULTI PURPOSE BUILDING(COVERED COURT)BRGY. PALO CANAMAN CAMARINES SURBuildings and Facilities | Completed | J-NAC CONSTRUCTION AND SUPPLY | ₱4.8M |