DPWH Sarangani DEO
DPWH implementing office 8eea76bc1314d4c8b49e
Overview
DPWH contracts
1,159
Total listed value
₱19.60B
Distinct contractors
181
More info
Largest contractors
J.G. ORANZA CONSTRUCTION₱670.1M
The largest contractor holds 6.3% of this office's listed value.
Latest 25 from a total of 1,159 records
| Contract ID | Start | Description | Status | Contractor | Amount |
|---|---|---|---|---|---|
| 23ME0088 | 3 yrs ago | CONSTRUCTION OF SOLAR WATER SYSTEM, SITIO TANDAWANAN, BARANGAY UPPER LUMABAT; MALUNGON, SARANGANI PROVINCEWater Provision and Storage | Completed | VERTICAL BUILDERS | ₱9.6M |
| 23ME0089 | 3 yrs ago | CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY PARAISO, ALABEL, SARANGANI PROVINCEWater Provision and Storage | Completed | EDCL CONSTRUCTION AND SUPPLY | ₱9.8M |
| 23ME0090 | 3 yrs ago | CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY KAPATAN, GLAN, SARANGANI PROVINCEWater Provision and Storage | Completed | JICLAM BUILDERS AND ENTERPRISES | ₱8.8M |
| 23ME0091 | 3 yrs ago | CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY KAWAYAN,MALUNGON,SARANGANI PROVINCEWater Provision and Storage | Completed | WILL & JOE AGGREGATES, INC. | ₱9.7M |
| 23ME0085 | 3 yrs 1 mo ago | CONSTRUCTION OF SOLAR WATER SYSTEM, BARANGAY UPO,MAITUM,SARANGANI PROVINCEWater Provision and Storage | Completed | VERGUZ CONSTRUCTION | ₱9.8M |
| 23ME0081 | 3 yrs 1 mo ago | CONSTRUCTION OF 1STY3CL, SALAKIT ELEMENTARY SCHOOL, KIAMBA, SARANGANI PROVINCEBuildings and Facilities | Completed | VERGUZ CONSTRUCTION | ₱7.4M |
| 23ME0084 | 3 yrs 1 mo ago | CONSTRUCTION OF 1STY3CL, MARGUS ELEMENTARY SCHOOL, GLAN, SARANGANI PROVINCEBuildings and Facilities | Completed | THREE MB BUILDERS | ₱6.8M |
| 23ME0082 | 3 yrs 1 mo ago | CONSTRUCTION OF 3CL, BANATE NATIONAL HIGH SCHOOL, MALUNGON, SARANGANI PROVINCEBuildings and Facilities | Completed | THE TRENDSETTER CONSTRUCTION AND SUPPLY CORP. | ₱7.5M |
| 23ME0083 | 3 yrs 1 mo ago | CONSTRUCTION OF 1STY3CL, MAASIM CES, MAASIM, SARANGANI PROVINCEBuildings and Facilities | Completed | SHEPPERD CONSTRUCTION AND SUPPLY | ₱7.4M |
| 23ME0080 | 3 yrs 2 mo ago | CONSTRUCTION OF LEGISLATIVE BUILDING (PHASE 8), MARIBULAN, ALABEL, SARANGANI PROVINCEBuildings and Facilities | Completed | ANNCORP BUILDERS, INC. | ₱29.4M |
| 23ME0017 | 3 yrs 3 mo ago | ASPHALT OVERLAY ALONG SDSCR K1741+312 - K1742+000, GLAN, SARANGANI PROVINCERoads | Completed | AGONG BUILDERS AND CONSTRUCTION SUPPLY, INC. | ₱27.1M |
| 23ME0033 | 3 yrs 3 mo ago | ASPHALT OVERLAY ALONG SARANGANI-DAVAO DEL SUR COASTAL ROAD-K1726+000-K1726+555, K1728+606-K1728+766, K1729+571-K1729+663, GLAN, SARANGANI PROVINCERoads | Completed | GEMMA CONSTRUCTION SUPPLY, INC.(FORMERLY:GEMMA CON | ₱31.3M |
| 23ME0032 | 3 yrs 3 mo ago | ASPHALT OVERLAY ALONG SDSCR, K1654+(-291)-K1654+(-206), K1654+(-206)-K1654+(-306), K1654+(-306)-K1654+000, K1654+000-K1654+395, ALABEL, SARANGANI PROVINCERoads | Completed | VICENTE T. LAO CONSTRUCTION | ₱29.8M |
| 23ME0078 | 3 yrs 3 mo ago | CONST. OF SLOPE PROTECTION AT NEW PUBLIC MARKET, MAASIM, SARANGANI PROVINCERoads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Rehabilitation - PCCP | Completed | THE TRENDSETTER CONSTRUCTION AND SUPPLY CORP. | ₱19.8M |
| 23ME0028 | 3 yrs 3 mo ago | CONST. OF MULTI-PURPOSE BUILDING INSIDE SARANGANI PROVINCIAL CAPITOL, ALABEL, SARANGANI PROVINCEBuildings and Facilities | Completed | KURDZ CONSTRUCTION | ₱9.9M |
| 23ME0074 | 3 yrs 3 mo ago | CONST. OF SOLAR WATER SYSTEM, BARANGAY TAMBAN, MALUNGON, SARANGANI PROVINCEWater Provision and Storage | Completed | DQMB CONSTRUCTION & SUPPLY CORP. | ₱9.8M |
| 23ME0075 | 3 yrs 3 mo ago | CONCRETING OF BRGY. LOMUYON - BRGY. MALIGANG FMR, BRGY. LOMUYON AND BRGY. MALIGANG, KIAMBA, SARANGANI PROVINCERoads | Completed | TSQUARE CONSTRUCTION CORPORATION (FORMERLY:T-SQUARE BUILDERS) | ₱11.9M |
| 23ME0076 | 3 yrs 3 mo ago | CONCRETING OF SITIO BAGO, BRGY. BLAAN FMR, BRGY. BLAAN, MALUNGON, SARANGANI PROVINCERoads | Completed | PASE CONSTRUCTION | ₱12.4M |
| 23ME0077 | 3 yrs 3 mo ago | CONCRETING OF PRK 11, SITIO KIBAWALAN, BRGY. MALUNGON GAMAY FMR, BRGY. MALUNGON GAMAY, MALUNGON, SARANGANI PROVINCERoads | Completed | BAYTORR CONSTRUCTION AND DEVELOPMENT CORPORATION | ₱12.4M |
| 23ME0069 | 3 yrs 4 mo ago | CLUSTER 1: 1. CONST. OF RAINWATER COLLECTION SYSTEM (RWCS) @ CABANSAL M. LARRY IPS, SITIO LUNAY, BRGY. AMSIPIT; 2. CONST. OF RAINWATER COLLECTION SYSTEM (RWCS) @ CALFUNGAL ES SITIO DATAL BAWING, BRGY. AMSIPIT; 3. CONST. OF RAINWATER COLLECTION SYSTEM (RWCWater Provision and Storage | Completed | LHE CONSTRUCTION & INDUSTRIAL SERVICES, INC. (FORMERLY: LHE CONSTRUCTION & ENG'G. SERVICES) | ₱2.3M |
| 23ME0070 | 3 yrs 4 mo ago | REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROAD ALONG SSKCR, K 1724+080-K1724+382, K1749+421-K1749+538, K1750+478.50-K1751+105.50, K1761+272.50-K1761+480, K1761+567.50-K1761+744.00, KIAMBA, SARANGANI PROVINCERoads | Completed | JDRC CONSTRUCTION & SUPPLIES, CORP. | ₱47.2M |
| 23ME0039 | 3 yrs 5 mo ago | WIDENING OF NAGPAN PARALLEL BR. ALONG DIGOS-MAKAR ROAD, MALUNGON, SARANGANI PROVINCEBridges: Construction - Concrete (Superstructure) - with Driven Piles, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry), Roads: Rehabilitation - PCCP | Completed | TSQUARE CONSTRUCTION CORPORATION (FORMERLY:T-SQUARE BUILDERS) | ₱17.4M |
| 23ME0007 | 3 yrs 6 mo ago | CONST. (COMPLETION) OF MPB @ LOMUYON, KIAMBA, SARANGANI PROVINCEBuildings and Facilities | Completed | VERTICAL BUILDERS | ₱3.0M |
| 23ME0020 | 3 yrs 6 mo ago | OFF-CARRAIGEWAY IMPROVEMENT ALONG SDSCR, K1656+648-K1664+371.43, ALABEL, SARANGANI PROVINCERoads | Completed | SHEPPERD CONSTRUCTION AND SUPPLY | ₱35.9M |
| 23ME0035 | 3 yrs 6 mo ago | REHAB/RECONST. OF ROADS W/ SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG MAITUM-LAKE SEBU RD, K1782+078.00-K1782+220.04, MAITUM, SARANGANI PROVINCERoads | Completed | CHARIFER BUILDERS,INC | ₱49.0M |