DPWH Baguio City DEO
DPWH implementing office eef461fa631a0a296db8
Overview
DPWH contracts
920
Total listed value
₱11.72B
Distinct contractors
177
More info
Level
DPWH office
Records span
Feb 2, 2016 – Jul 6, 2026
Largest contractors
A.P.B. CONSTRUCTION₱380.4M
The largest contractor holds 41.7% of this office's listed value.
Latest 25 from a total of 920 records
| Contract ID | Start | Description | Status | Contractor | Amount |
|---|---|---|---|---|---|
| 15PD0038 | 10 yrs 9 mo ago | CONST/MAINT OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, 4. CONST/REH OF FLOOD MITIGATION FACILITIES ALONG BALILI RIVER, BAGUIO CITY LDFlood Control and Drainage | Completed | GOLDRICH CONSTRUCTION AND TRADING | ₱46.2M |
| 15PD0040 | 10 yrs 9 mo ago | LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF COVERED COURT AT SLU-SVP, BAGUIO CITYBuildings and Facilities | Completed | H.D. DE CASTRO CONSTRUCTION | ₱2.9M |
| 15PD0041 | 10 yrs 9 mo ago | LOCAL INFRASTRUCTURE PROGRAM- CONSTRUCTION OF MULTI-PURPOSE AT MALAYA, DOMINICAN-MIRADOR, BAGUIO CITY LONE DISTRICTBuildings and Facilities | Completed | HGW=3 ENGINEERING & CONSTRUCTION | ₱1.9M |
| 15PD0044 | 10 yrs 9 mo ago | LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF COVERED COURT AT LOURDES PROPER, BAGUIO CITY LONE DISTRICTBuildings and Facilities | Completed | CM-AL CONSTRUCTION AND AGGREGATES | ₱1.9M |
| 15PD0048 | 10 yrs 9 mo ago | LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF MULTI-PURPOSE HALL BUILDING AT CAMDAS, BAGUIO CITY LONE DISTRICTBuildings and Facilities | Completed | HDG CONSTRUCTION AND ENTERPRISES | ₱939.5K |
| 15PD0049 | 10 yrs 9 mo ago | CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION STRUCTURES/DRAINAGE SYSTEM ALONG CITY CAMP LAGOON FLOOD CONTROL, CITY CAMP LAGOON, BAGUIO CITYFlood Control/Hydraulics/Drainage, Flood Control/Hydraulics/River Control, Maintenance Flood Control | Completed | JOMARCANN GENERAL CONSTRUCTION | ₱47.0M |
| 15PD0050 | 10 yrs 9 mo ago | LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION/EXTENSION OF BARANGAY HALL AT LOAKAN LIWANAG, BAGUIO CITY LONE DISTRICTBuildings and Facilities | Completed | SEGAL CONSTRUCTION | ₱957.4K |
| 15PD0065 | 10 yrs 9 mo ago | LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF INCOME GENERATING PARKING SPACE AT PUROK 7, PINSAO PILO PROJECT, BAGUIO CITY LONE DISTRICTBuildings and Facilities | Completed | LOC CONSTRUCTION AND SUPPLY | ₱1.9M |
| 15PD0067 | 10 yrs 9 mo ago | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS, BALATOC RD. KO248+370-KO248+782Roads | Completed | A.P.B. CONSTRUCTION | ₱9.4M |
| 15PD0071 | 10 yrs 9 mo ago | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS, MAGSAYSAY AVE. (TRINIDAD RD.)KO251+368-KO251+104Roads | Completed | A.P.B. CONSTRUCTION | ₱7.7M |
| 15PD0034 | 10 yrs 9 mo ago | CONST/MAINT OF FL MITIGATION STRUCT AND DRAIN SYST 3. CONST/REH. OF FLOOD MITIGATION ALONG BUED RIVER, BC, LDFlood Control/Hydraulics/Drainage, Flood Control/Hydraulics/River Control, Maintenance Flood Control | Completed | JOMARCANN GENERAL CONSTRUCTION | ₱47.1M |
| 15PD0031 | 10 yrs 9 mo ago | CONTRACT PACKAGE 7: ASSET PRESERVATION OF NATL RDS A) PREV. MAINT. BASED ON PAVT MGMT SYST/HWAY DEVT & MGMT 4 (HDM-4)(INT. SEC) A) MAGSAYSAY AVE. (TRINIDAD RD) (S00525LZ), CHAINAGE 0-264 B) MAGSAYSAY AVE (TRINIDAD RD) (S00483LZ), KO251+479-KO251+554 C) MRoads | Completed | GOLDRICH CONSTRUCTION AND TRADING | ₱4.7M |
| 15PD0032 | 10 yrs 9 mo ago | CONTRACT PACKAGE 8: ASSET PRESERVATION OF NATL RDS. A) PREV. MAINT BASED ON PAVT MGMT SYST/HWAY DEVT & MGMT-4 (HDM-4)(INT. SECT): A)MAGSAYSAY AVE (TRINIDAD RD) EAST SERVICE (S00523LZ) CHAINAGE 0-21 B) CHANUM ST. (S00447LZ) CHAINAGE 0-490 C) CHUNTUG#1 (S00Roads | Completed | GOLDRICH CONSTRUCTION AND TRADING | ₱12.9M |
| 24PD0084 | — | CONTRACT PACKAGE 8: REHABILITATION OF DISASTER-RELATED INFRASTRUCTURE AND OTHER FACILITIES: REHABILITATION/ RECONSTRUCTION OF INFRASTRUCTURE WHICH WERE DAMAGED BY COMBINED EFFECTS SOUTHWEST MONSOON, TYPHOON 'EGAY' AND PREVIOUS TYPHOONS: A. KAYANG ST - CRoads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry) | For Procurement | — | ₱0 |
| 24PD0085 | — | CONTRACT PACKAGE 9: REHABILITATION DISASTER-RELATED INFRASTRUCTURE AND OTHER FACILITIES: A. REPAIR/REHAB/RESTORATION OF MARCOS HI-WAY (S00432LZ) K0280+(-500) -K0280+(-480) WHICH WAS DAMAGED BY TY 'CARINA' LAST JULY 24, 2024 (ITEM A) B; REP/REHAB/REST. OFRoads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry) | For Procurement | — | ₱0 |
| 24PD0091 | — | REHABILITATION OF DISASTER-RELATED INFRASTRUCTURE AND OTHER FACILITIES-REPAIR/REHABILITATION OF DAMAGED SLOPE PROTECTION ALONG EASTERN LINK CIRCUMFERENTIAL ROAD, K0247+925-K0247+985, BAGUIO CITY WHICH WAS DAMAGED BY TYPHOON 'CARINA' LAST JULY 2024Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry) | For Procurement | — | ₱0 |
| 25PD0039 | — | BASIC INFRASTRUCTURE PROGRAM (BIP) REHABILITATION OF ROADS WITH SLOPE PROTECTION STRUCTURES AND DRAINAGE STRUCTURES, BARANGAY LOAKAN-APUGAN AND BARANGAY LOAKAN LIWANAG, BAGUIO CITYRoads | For Procurement | — | ₱0 |
| 25PD0040 | — | BASIC INFRASTRUCTURE PROGRAM (BIP) REHABILITATION OF ROAD WITH DRAINAGE STRUCTURE, BARANGAY IRISAN, BAGUIO CITYRoads | For Procurement | — | ₱0 |
| 25PD0041 | — | BASIC INFRASTRUCTURE PROGRAM (BIP) CONSTRUCTION OF ROAD, STO. TOMAS PROPER AND SAN CARLOS HEIGHTS BARANGAY IRISAN, BAGUIO CITYRoads | For Procurement | — | ₱0 |
| 25PD0042 | — | BASIC INFRASTRUCTURE PROGRAM (BIP) REHABILITATION OF ROAD, BARANGAY CAMP 7, BAGUIO CITYRoads | For Procurement | — | ₱0 |
| 25PD0045 | — | BASIC INFRASTRUCTURE PROGRAM (BIP) REHABILITATION OF ROAD WITH DRAINAGE STRUCTURE, PUROK 1, 2 AND 3, BARANGAY DPS AREA, BAGUIO CITYRoads | For Procurement | — | ₱0 |
| 25PD0048 | — | BASIC INFRASTRUCTURE PROGRAM (BIP) REHABILITATION OF ROAD, TORRES BUGALLON ROAD, BARANGAY WEST MODERNSITE, BAGUIO CITYRoads | For Procurement | — | ₱0 |
| 25PD0049 | — | BASIC INFRASTRUCTURE PROGRAM (BIP) - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION STRUCTURE, PUROK 4, BARANGAY BAKAKENG NORTE/SUR, BAGUIO CITYRoads | For Procurement | — | ₱0 |
| 25PD0050 | — | BASIC INFRASTRUCTURE PROGRAM (BIP) REHABILITATION OF ROAD, BARANGAY TRANCOVILLE, BAGUIO CITYRoads | For Procurement | — | ₱0 |
| 25PD0061 | — | CONTRACT PACKAGE 9: BASIC INFRASTRUCTURE PROGRAM (BIP) A. CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT BARANGAY EAST MODERNSITE, BAGUIO CITY B. CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BUILDING B), BARANGAY EAST MODERNSITE, BAGUIO CIBuildings | For Procurement | — | ₱0 |