DPWH Pangasinan 2nd DEO
DPWH implementing office ffad5cdfbfd074da7d1b
Overview
DPWH contracts
1,901
Total listed value
₱19.56B
Distinct contractors
136
More info
Largest contractors
ALCEL CONSTRUCTION₱1.24B
The largest contractor holds 22.2% of this office's listed value.
Latest 25 from a total of 1,901 records
| Contract ID | Start | Description | Status | Contractor | Amount |
|---|---|---|---|---|---|
| 24AH0152 | 2 yrs 7 mo ago | CONCRETING OF BRGY.LELEMAAN FMR, BRGY.LELEMAAN, MANAOAG, PANGASINANRoads | Completed | MIGHTYWAY CONSTRUCTION AND SUPPLY | ₱9.9M |
| 24AH0153 | 2 yrs 7 mo ago | CONCRETING OF BRGY. ANOLID FMR, BRGY. ANOLID, MANGALDAN, PANGASINANRoads | Completed | J.G. GARCIA CONSTRUCTION & SUPPLY | ₱9.9M |
| 24AH0154 | 2 yrs 7 mo ago | CONCRETING OF BRGY. MANLOCBOC TO BRGY. POBLACION FMR, BRGY. MANLOCBOC AND BRGY. POBLACION,AGUILAR,PAGAA 2024 DA FMR | Completed | BMK CONSTRUCTION CORPORATION | ₱49.8M |
| 24AH0113 | 2 yrs 7 mo ago | CONSTRUCTION OF ROAD AND DRAINAGE BARANGAY POBLACION, SAN FABIAN, PANGASINANRoads | Completed | J.G. GARCIA CONSTRUCTION & SUPPLY | ₱4.9M |
| 24AH0116 | 2 yrs 7 mo ago | CONSTRUCTION OF OPEN DRAINAGE CANAL, BRGY. NIBALIW MAGLIBA, SAN FABIAN, PANGASINANGAA 2024 SSP | Completed | J.G. GARCIA CONSTRUCTION & SUPPLY | ₱19.8M |
| 24AH0121 | 2 yrs 7 mo ago | CONSTRUCTION OF ROAD,BARANGAY CALUMBOYAN NORTE, MANGATAREM, PANGASINANRoads | Completed | SOLID STAR BUILDERS AND CONSTRUCTION SUPPLY | ₱6.1M |
| 24AH0122 | 2 yrs 7 mo ago | CONSTRUCTION OF ROAD, BARANGAY LAOAG, AGUILAR, PANGASINANRoads | Completed | SOLID STAR BUILDERS AND CONSTRUCTION SUPPLY | ₱4.9M |
| 24AH0123 | 2 yrs 7 mo ago | CONSTRUCTION OF ROAD, BARANGAY POBLACION, LINGAYEN, PANGASINANGAA 2024 SSP | Completed | SOLID STAR BUILDERS AND CONSTRUCTION SUPPLY | ₱6.1M |
| 24AH0124 | 2 yrs 7 mo ago | CONSTRUCTION OF ROAD, BRGY. QUIBAOL, LINGAYEN, PANGASINANRoads | Completed | SOLID STAR BUILDERS AND CONSTRUCTION SUPPLY | ₱6.1M |
| 24AH0125 | 2 yrs 7 mo ago | CONSTRUCTION OF BARANGAY ROAD, BARANGAY SUACO, MANGATAREM, PANGASINANRoads | Completed | SOLID STAR BUILDERS AND CONSTRUCTION SUPPLY | ₱6.1M |
| 24AH0127 | 2 yrs 7 mo ago | REHABILITATION OF ROAD, BRGY. BASING, BINMALEY, PANGASINANRoads | Completed | SOLID STAR BUILDERS AND CONSTRUCTION SUPPLY | ₱5.0M |
| 24AH0128 | 2 yrs 7 mo ago | CONSTRUCTION OF ROAD,BARANGAY SAN JOSE-BRGY.LAOIS, LABRADOR, PANGASINANGAA 2024 SSP | On-Going | SOLID STAR BUILDERS AND CONSTRUCTION SUPPLY | ₱5.0M |
| 24AH0129 | 2 yrs 7 mo ago | CONSTRUCTION OF ROAD, BRGY.DORONGAN VALERIO-BRGY. CBN, MANGATAREM, PANGASINANRoads | Completed | SOLID STAR BUILDERS AND CONSTRUCTION SUPPLY | ₱5.0M |
| 24AH0130 | 2 yrs 7 mo ago | CONSTRUCTION OF RIVER BANK PROTECTION, BARANGAY SAN JOSE, AGUILAR, PANGASINANFlood Control and Drainage | Completed | MIGHTYWAY CONSTRUCTION AND SUPPLY | ₱9.9M |
| 24AH0132 | 2 yrs 7 mo ago | CONSTRUCTION OF MULTI PURPOSE BUILDING PHASE II, BRGY. TONTON, LINGAYEN, PANGASINANBuildings and Facilities | Completed | BRYLLE TRADING & CONSTRUCTION SUPPLIES | ₱5.0M |
| 24AH0147 | 2 yrs 7 mo ago | CONCRETING OF BRGY.ANONANG FMR, BRGY. ANONANG, SAN FABIAN, PANGASINANGAA 2024 DA FMR | On-Going | MIGHTYWAY CONSTRUCTION AND SUPPLY | ₱14.5M |
| 24AH0144 | 2 yrs 7 mo ago | CONSTRUCTION OF RIVER PROTECTION ALONG AGNO RIVER BASIN, BRGY.POBLACION(UPSTREAM),URBIZTONDO,PANGASIGAA 2024 OO-2 | On-Going | ANORE CONSTRUCTION | ₱96.5M |
| 24AH0014 | 2 yrs 8 mo ago | ASSET PRESERVATION-REHAB/RECONST'N./UPGRADING OF DAMAGED PAVED ROADS ALONG URDANETA JCT-DAGUPAN-LINGRoads | Completed | R.A. MATIAS CONSTRUCTION AND DEVELOPERS INC. (FORMERLY : R.A. MATIAS CONSTRUCTION AND DEVELOPERS) | ₱13.2M |
| 24AH0015 | 2 yrs 8 mo ago | ASSET PRESERVATION-CONST'N./UPGRADING/REHAB.FOR DRAINAGE-JUDGE JOSE DE VENECIA SR.AVE-K0209+500-K020Roads | Completed | MIGHTYWAY CONSTRUCTION AND SUPPLY | ₱4.3M |
| 24AH0032 | 2 yrs 8 mo ago | INSTALLATION OF SIGNAGE-WARNING,ADVISORY & REGULATORY SIGNS,PAVEMENT MARKINGS,PEDESTRIAN FENCING,& SRoads | Completed | BET CONSTRUCTION & SUPPLY | ₱9.8M |
| 24AH0039 | 2 yrs 8 mo ago | CONSTRUCTION OF ROAD INCLUDING DRAINAGE SYSTEM AT BRGY. HERRERO PEREZ PHASE 1,DAGUPAN CITY, PANGASINGAA 2024 SSP | Completed | J.G. GARCIA CONSTRUCTION & SUPPLY | ₱4.9M |
| 24AH0043 | 2 yrs 8 mo ago | CONSTRUCTION OF ROAD AND DRAINAGE SYSTEM AT BARANGAY HERRERO PEREZ, DAGUPAN CITY,PANGASINANRoads | Completed | ZOTA TRADING & CONSTRUCTION | ₱5.0M |
| 24AH0059 | 2 yrs 8 mo ago | CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING AT BRGY. BUCAO, MANAOAG,PANGASINANBuildings and Facilities | Completed | BMK CONSTRUCTION CORPORATION | ₱3.0M |
| 24AH0062 | 2 yrs 8 mo ago | CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING AT BRGY. COLISAO,SAN FABIAN, PANGASINANBuildings and Facilities | Completed | J.G. GARCIA CONSTRUCTION & SUPPLY | ₱3.0M |
| 24AH0069 | 2 yrs 8 mo ago | CONSTRUCTION(COMPLETION)OF MULTI-PURPOSE BUILDING AT BRGY.NIBALIW MAGLIBA, SAN FABIAN, PANGASINANBuildings and Facilities | Completed | J.G. GARCIA CONSTRUCTION & SUPPLY | ₱3.0M |