Regionwide / Nationwide — Roads and Bridges — Feasibility Studies/ Preliminary and Detailed Engineering/ Economic Analysis/ Technical Studies/ Traffic Impact Assessment — Region IX — Phase III of Pitogo-Tabina Coastal Road, Zamboanga del Sur
Department of Public Works and Highways (DPWH) · GAA program line
Program ID:
10517f1015e299e2
Agency code:
18-001
FY2026 appropriation:
₱10,300,000.00 · 1 line items
FY2025 appropriation:
₱1,300,000.00
Source key:
18-001|regionwide nationwide roads and bridges feasibility studies preliminary and detailed engineering economic analysis technical studies traffic impact assessment region ix phase iii of pitogotabina coastal road zamboanga del sur
Appropriation per year
Source: Philippine Budget Data API (BetterGov.ph), https://budget.bettergov.ph/api/v1 (CC BY 4.0), snapshot Nov 10, 2026. A program line is an authority to spend, not proof of spending. ₱10.3M in FY2026.