EDDMARI CONSTRUCTION & TRADING
Contractor 344bf7e5fbcac53728ad
Overview
PhilGEPS awards
₱18.33B · 459 awards
DPWH contracts
₱9.95B · 194 contracts
Rank by recorded value
#86 of 23,487
More info
First record
Oct 21, 2008 (18 yrs ago)
Latest record
Dec 2, 2025 (11 mos ago)
DPWH contractor code
20301
Where they work
Latest 25 from a total of 194 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 19CG0053 | 7 yrs 1 mo ago | CONSTRUCTION OF CONCRETE SLOPE PROTECTION OF TAIL DIKE (STO. TOMAS - MINALIN SECTION), STO. TOMAS AND MINALIN, PAMPANGAFlood Control and Drainage | Completed | Pampanga 1st DEO | ₱46.5M |
| 19CG0098 | 7 yrs 2 mo ago | ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS MANILA NORTH ROAD - K0057+920 - K0058+140, K0058+275 - K0059+000, K0063+800 - K0064+018Roads | Completed | Pampanga 1st DEO | ₱87.5M |
| 19CG0166 | 7 yrs 2 mo ago | CONSTRUCTION OF ROAD AND CONCRETE SLOPE PROTECTION (LAND SIDE) OF TAIL DIKE, STO. TOMAS - SAN FERNANDO, PAMPANGA (STO. TOMAS SECTION), STO. TOMAS, PAMPANGAFlood Control and Drainage | Completed | Pampanga 1st DEO | ₱46.4M |
| 19CG0136 | 7 yrs 4 mo ago | CONSTRUCTION OF 4 - CLASSROOM SCHOOL BUILDING SAN LUIS CS ANNEX, STA. LUCIA, SAN LUIS, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱5.6M |
| 19C00015 | 7 yrs 4 mo ago | NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LUBA0-GUAGUA-MINALIN-STO. TOMAS ROAD (STO. TOMAS-MINALIN SECTION) PAMPANGA 4TH LEGISLATIVE DISTRICT, PAMPANGARoads | Completed | Region III | ₱144.0M |
| 19CG0035 | 7 yrs 4 mo ago | CONSTRUCTION OF CONCRETE SLOPE PROTECTION OF STA. CATALINA DIKE, MINALIN, PAMPANGAFlood Control and Drainage | Completed | Pampanga 1st DEO | ₱91.4M |
| 19CG0057 | 7 yrs 4 mo ago | CONSTRUCTION OF SLOPE PROTECTION OF PAMPANGA DELTA DIKE, MACABEBE - MASANTOL, PAMPANGAFlood Control and Drainage | Completed | Pampanga 1st DEO | ₱82.5M |
| 19CG0099 | 7 yrs 4 mo ago | REHABILITATION/ REPAIR/ IMPROVEMENT OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY LOURDES, MINALIN, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱474.3K |
| 19CG0103 | 7 yrs 4 mo ago | REHABILITATION/ REPAIR/ IMPROVEMENT OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SAN PEDRO, SAN SIMON, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱949.8K |
| 19OB0181 | 7 yrs 4 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT C6, BRGY. LOWER BICUTAN, TAGUIG CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱46.9M |
| 19CG0016 | 7 yrs 5 mo ago | CONSTRUCTION/ REHABILITATION OF SAN ANTONIO - CONCEPCION CREEK, BACOLOR, PAMPANGA (R.A. 9506- BACOLOR REHABILITATION ACT)Flood Control and Drainage | Completed | Pampanga 1st DEO | ₱18.5M |
| 18CG0469 | 7 yrs 10 mo ago | CONSTRUCTION OF FOUR-STOREY, TWENTY(20) CLASSROOMS SCHOOL BUILDING - STA. MARIA HIGH SCHOOL, MINALIN, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱42.6M |
| 18CG0470 | 7 yrs 10 mo ago | CONSTRUCTION OF 2 UNITS TWO(2) STOREY, FOUR (4) AND 2 UNITS TWO (2) STOREY, SIX (6) CLASSROOM SCHOOL BUILDING AT STA. LUCIA MATUA ES, MASANTOL, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱48.8M |
| 18CG0471 | 7 yrs 10 mo ago | CONSTRUCTION OF 3 UNITS - FOUR (4)- STOREY, EIGHT(8) CLASSROOM SCHOOL BUILDING AT MACABEBE CENTRAL ES, MACABEBE, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱57.9M |
| 18CG0472 | 7 yrs 10 mo ago | CONSTRUCTION OF 3 UNITS - FOUR (4)- STOREY, EIGHT(8) CLASSROOM AND 1 UNIT - TWO (2)- STOREY, SIX (6) CLASSROOM SCHOOL BUILDING AT SAN MATIAS NHS, STO. TOMAS, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱69.8M |
| 18CG0440 | 7 yrs 10 mo ago | CONSTRUCTION OF THREE(3) STOREY, TWELVE (12) CLASSROOM SCHOOL BUILDING AT POBLACION HS, SANTO TOMAS, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱31.9M |
| 18CG0441 | 7 yrs 10 mo ago | CONSTRUCTION OF THREE(3) STOREY, TWELVE (12) CLASSROOM SCHOOL BUILDING AT SAN BARTOLOME ES, SANTO TOMAS, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱31.9M |
| 18CG0442 | 7 yrs 10 mo ago | CONSTRUCTION OF THREE(3) STOREY, TWELVE (12) CLASSROOM SCHOOL BUILDING AT SAN MATIAS ES, SANTO TOMAS, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱31.9M |
| 18CG0448 | 7 yrs 10 mo ago | CONSTRUCTION OF THREE-STOREY, FIFTEEN (15) CLASSROOM SCHOOL BUILDING AT BEBE ANAC ES, MASANTOL, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱34.0M |
| 18C00083 | 7 yrs 10 mo ago | LOCAL PROGRAMS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION/IMPROVMENT/UPGRADING OF LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (PHASE 3), PAMPANGARoads | Completed | Region III | ₱138.2M |
| 18C00085 | 7 yrs 10 mo ago | LOCAL PROGRAMS-LOCAL ROADS AND BRIDGES-LOCAL ROADS, CONSTRUCTION/IMPROVEMENT/UPGRADING OF LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (PHASE 5), PAMPANGARoads | Completed | Region III | ₱132.9M |
| 18CG0350 | 8 yrs 1 mo ago | LOCAL INFRASTRUCTURE PROGRAM - REHABILITATION OF STA. MONICA MULTI-PURPOSE BUILDING, SAN LUIS, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱948.0K |
| 18CG0360 | 8 yrs 1 mo ago | REHABILITATION/IMPROVEMENT OF SAN JUAN MULTI-PURPOSE BUILDING (OLD MUNICIPAL HALL/BARANGAY HALL), SAN SIMON, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱2.3M |
| 18CG0361 | 8 yrs 1 mo ago | REHABILITATION OF PALIGUI SENIOR MULTI-PURPOSE COVERED COURT, PALIGUI, CANDABA, PAMPANGABuildings and Facilities | Completed | Pampanga 1st DEO | ₱2.8M |
| 18CG0373 | 8 yrs 1 mo ago | REHABILITATION OF ERODED BANKS ALONG PAMPANGA RIVER APALIT SAN SIMON, SAN LUIS & CANDABA, PAMPANGA, SAN LUIS, PAMPANGAFlood Control and Drainage | Completed | Pampanga 1st DEO | ₱47.0M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.