Skip to content
FY2026 GAA: ₱6.79T
PisoScan

ORIENTAL SALES CENTER AND CONTRACTOR

Contractor 3a3aba57f54f40a1817f

Overview

PhilGEPS awards
₱5.62B · 408 awards
DPWH contracts
₱4.10B · 158 contracts
Rank by recorded value
#352 of 23,487

More info

First record
Jun 10, 2008 (18 yrs 5 mo ago)
Latest record
Jun 9, 2026 (5 mos ago)
DPWH contractor code
33630

Where they work

Pangasinan₱8.01B
La Union₱425.7M
Abra₱243.6M
Nueva Ecija₱96.5M
Ilocos Sur₱72.4M
Latest 25 from a total of 158 DPWH contracts
Contract IDStartDescriptionStatusOfficeAmount
17PA01189 yrs 1 mo agoREPAIR/REHABILITATION/IMPROVEMENT OF ABRA-KALINGA ROAD ASPHALT OVERLAY WITH THERMOPLASTIC PAVEMENT MARKINGS, A.) KO424+492 - KO426+343; B.) KO435+551 - KO437+441RoadsCompletedAbra DEO₱23.0M
17PA01209 yrs 1 mo agoREPAIR/REHABILITATION/IMPROVEMENT OF ABRA-KALINGA ROAD ASPHALT OVERLAY WITH THERMOPLASTIC PAVEMENT MARKINGS, A.) 429+850 - KO435+456RoadsCompletedAbra DEO₱34.6M
17PA01219 yrs 1 mo agoREPAIR/REHABILITATION/IMPROVEMENT OFABRA- ILOCOS NORTE ROAD ASPHALT OVERLAY WITH THERMOPLASTIC PAVEMENT MARKINGS, KO413+000 - KO416+818RoadsCompletedAbra DEO₱35.6M
17AJ00889 yrs 1 mo agoCONCRETING OF BRGY. MAGTAKING FMR, SAN CARLOS CITY, PANGASINANRoadsCompletedPangasinan 4th DEO₱1.9M
17AJ00899 yrs 1 mo agoCONCRETING OF BRGY. PIAS FMR, MAPANDAN, PANGASINANRoadsCompletedPangasinan 4th DEO₱1.9M
17AJ00909 yrs 1 mo agoCONCRETING OF BRGY. BELENG FMR, BAYAMBANG, PANGASINANRoadsCompletedPangasinan 4th DEO₱1.9M
17AI01029 yrs 5 mo agoIMPVT/WIDENING OF NATL RD ALONG BINALONAN-ASINGAN-STA. MARIA ROAD W/ RROW ACQUISITION, KO 186+850-KORoadsCompletedPangasinan 3rd DEO₱43.1M
17AH01149 yrs 6 mo agoREPAIR/REHAB./IMPROV'T.(ASPHALT OVERLAY)ALONG LABRADOR-LINGAYEN RD.,K0366+900-K0368+600RoadsCompletedPangasinan 2nd DEO₱11.5M
17AH01119 yrs 6 mo agoREPAIR/REHAB./IMPRV'T.(ASPHALT OVERLAY)ALONG PANG.-ZAMBALES RD.,K0348+000-K0353+636RoadsCompletedPangasinan 2nd DEO₱37.2M
17AH01129 yrs 6 mo agoREPAIR/REHAB./IMPRV'T.(ASPHALT OVERLAY)ALONG PANG.-ZAMBALES RD.K0341+(-841)-K0344+000RoadsCompletedPangasinan 2nd DEO₱25.8M
17AH01139 yrs 6 mo agoREPAIR/REHAB./IMPV'T.(ASPHALT OVERLAY)ALONG LINGAYEN CAPITOL LOOP (LS)K0364+(-219)-K0364+836RoadsCompletedPangasinan 2nd DEO₱11.7M
17AJ00369 yrs 6 mo agoASSET PRESERVATION OF NATIONAL ROADS, PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM / HDM-4, JUDGE JOSE DE VENECIA SR. AVE., K0.207+000 TO K0.207+073; K0.207+(-)611 TO K0.207+000; K0.207+(-)711 TO K0.207+(-)611, CALASIAO, PANGASINANRoadsCompletedPangasinan 4th DEO₱6.6M
17AJ00489 yrs 6 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY AMBAYAT II, BAYAMBANG, PANGASINANBuildings and FacilitiesCompletedPangasinan 4th DEO₱2.9M
17AJ00519 yrs 6 mo agoCONSTRUCTION OF FLOOD CONTROL/DRAINAGE PROJECT, ZONE 1-7, POBLACION SUR, BAYAMBANG, PANGASINANFlood Control and DrainageCompletedPangasinan 4th DEO₱4.6M
16AI02539 yrs 9 mo agoPREVENTIVE MAINT. BASED ON PAVEMENT MGMT SYSTEM/HIGHWAY DEVT & MGMT-4 (HDM-4) (INTERMITTENT SECTIONSRoadsCompletedPangasinan 3rd DEO₱18.7M
16AJ006010 yrs 6 mo agoCONSTRUCTION OF TECHNICAL AND VOCATIONAL - LIVELIHOOD LABORATORY BUILDING AT DANIEL MARAMBA NATIONALBuildings and FacilitiesCompletedPangasinan 4th DEO₱2.4M
16AJ004510 yrs 7 mo agoPREVENTIVE MAINTENANCE ALONG CAMILING-WAWA-BAYAMBANG-MALASIQUI-STA. BARBARA ROAD, K0.178+000-K0.178RoadsCompletedPangasinan 4th DEO₱10.4M
16AJ002310 yrs 7 mo agoIMPROVEMENT/CONSTRUCTION/UPGRADING/REHABILITATION, VILLASIS-MALASIQUI-SAN CARLOS ROAD, K0.193+182 -RoadsCompletedPangasinan 4th DEO₱21.0M
16AI002610 yrs 7 mo agoPREVENTIVE MAINTENANCE BASED ON PAVEMENT MGMT SYSTEM/HIGHWAY DEVT & MGMT-4(HDM-4) (INTERMITTEN SECTIRoadsCompletedPangasinan 3rd DEO₱23.3M
16A0005610 yrs 8 mo agoIMPROVEMENT/WIDENING OF NATIONAL ROADS, OUTSIDE N1, JUDGE JOSE DE VENECIA SR. AVENUE (S05985LZ), K0207+(-711) - K0207+073; K0207+700 - K0207+870RoadsCompletedRegion I₱28.7M
15AI041910 yrs 8 mo agoPREVENTIVE MAINT BASED ON PAVEMENT MGMT SYSTEM/HIGHWAY DEVT & MGMT-4 (HDM-4) (INTERMITTENT SECTIONS)RoadsCompletedPangasinan 3rd DEO₱15.1M
15AI042010 yrs 8 mo agoPREVENTIVE MAINT BASED ON PAVEMENT MGMT SYSTEM/HIGHWAY DEVT & MGMT-4 (HDM-4) (INTERMITTENT SECTIONS)RoadsCompletedPangasinan 3rd DEO₱30.3M
16AJ003110 yrs 9 mo agoREHABILITATION/RECONSTRUCTION/UPGRADING ALONG STA. BARBARA-MANGALDAN ROAD, K0.201+(-160) - K0.201+14RoadsCompletedPangasinan 4th DEO₱39.7M
16AJ003310 yrs 9 mo agoPREVENTIVE MAINTENANCE ALONG CARMEN JCT.- BAYAMBANG-MANAT ROAD, K0.190+(-478) - K0.190+169, BAYAMBANRoadsCompletedPangasinan 4th DEO₱4.8M
16AJ001610 yrs 10 mo agoPREVENTIVE MAINTENANCE ALONG URDANETA JCT.-DAGUPAN ROAD K0.202+409 - K0.203+453, K0.204+125 - K0.205RoadsCompletedRegion I₱24.8M

Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.