MAR-VEL CONSTRUCTION & SUPPLY
Contractor 4e89e9e69f55cac3f6ca
Overview
PhilGEPS awards
₱527.6M · 85 awards
DPWH contracts
₱4.95B · 169 contracts
Rank by recorded value
#625 of 23,487
More info
First record
Nov 29, 2006 (19 yrs 11 mo ago)
Latest record
Sep 9, 2026 (2 mos ago)
DPWH contractor code
23722
Where they work
Latest 25 from a total of 169 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 18DG0032 | 8 yrs 9 mo ago | ROAD WIDENING-TERTIARY ROADS-CRISANTO M. DELOS REYES AVE-K0068+495-K0068+998, TAGAYTAY CITYRoads | Completed | Cavite 2nd DEO | ₱20.6M |
| 17DH0104 | 8 yrs 11 mo ago | CONSTRUCTION OF THREE (3) STOREY, TWELVE (12) CLASSROOM SCHOOL BUILDING, PILA E/S, PILA, LAGUNABuildings and Facilities | Completed | Laguna 1st DEO | ₱28.9M |
| 17DH0108 | 8 yrs 11 mo ago | CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, GOV. FELICISIMO T. SAN LUIS NATIONAL AGRO-INDUSTRIAL HIGH SCHOOL, SINILOAN, LAGUNABuildings and Facilities | Completed | Laguna 1st DEO | ₱16.7M |
| 17DH0101 | 8 yrs 11 mo ago | CONSTRUCTION OF THREE (3) STOREY, TWELVE (12) CLASSROOM SCHOOL BUILDING, LAGUNA SENIOR HIGH SCHOOL (SITE # 1), STA. CRUZ, LAGUNABuildings and Facilities | Completed | Laguna 1st DEO | ₱29.3M |
| 17DH0102 | 8 yrs 11 mo ago | CONSTRUCTION OF THREE (3) STOREY, TWELVE (12) CLASSROOM SCHOOL BUILDING, LAGUNA SENIOR HIGH SCHOOL (SITE # 2), STA. CRUZ, LAGUNABuildings and Facilities | Completed | Laguna 1st DEO | ₱29.3M |
| 17DP0006 | 9 yrs 9 mo ago | NETWORK DEVELOPMENT - IMPROVEMENT / WIDENING OF NATIONAL ROADS ALONG SAN PABLO-RIZAL - NAGCARLAN - LILIW RD. (S05817LZ) K0095 + 465 - K0096 + 912Flood Control/Hydraulics/Drainage, Roads: Construction - PCCP | Completed | Laguna 3rd DEO | ₱48.3M |
| 17DH0022 | 9 yrs 9 mo ago | NETWORK DEVELOPMENT, OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE, SECONDARY ROADS, IMPROVEMENT OF INTERSECTION ALONG CALAMBA-STA. CRUZ-FAMY JCT. ROAD, K0105 + 620Roads | Completed | Laguna 1st DEO | ₱11.3M |
| 16DH0055 | 10 yrs 2 mo ago | CONSTRUCTION OF THREE (3) STOREY, TWELVE (12) CLASSROOM SCHOOL BUILDING, LUMBAN NATIONAL HIGH SCHOOL, LUMBAN, LAGUNABuildings and Facilities | Completed | Laguna 1st DEO | ₱19.0M |
| 16DH0056 | 10 yrs 2 mo ago | CONSTRUCTION OF FOUR (3) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, PAGSANJAN NATIONAL HIGH SCHOOL, PAGSANJAN, LAGUNABuildings and Facilities | Completed | Laguna 1st DEO | ₱14.4M |
| 16DH0009 | 10 yrs 7 mo ago | CLUSTER I - CONCRETING OF FARM TO MARKET ROADS:A. PUROK 2, BRGY. SAN JUAN, STA. CRUZ, LAGUNA, 4TH LD; B. SITIO HINGIWAN-BRGY.BAGONG POOK,, BRGY. BAGONG POOK, PILA, LAGUNA; C. BRGY. MASICO-BRGY. SAN MIGUEL, BRGY. MASICO, PILALAGUNA, 4TH LD D. BRGY. STARoads | Completed | Laguna 1st DEO | ₱11.6M |
| 15DI0180 | 10 yrs 7 mo ago | IMPROVEMENT/ WIDENING OF NATIONAL ROADS -SECONDARY ROADS - ACCESS TO SLEX MAMPLASAN EXIT, STA. 000+000.00 - STA. 000+130.00Roads | Completed | Region IV-A | ₱4.7M |
| 16DP0003 | 10 yrs 7 mo ago | LOCAL INFRASTRUCTURE PROGRAM REHABILITATION/IMPROVEMENT OF ROAD CALAUAN NAGCARLAN K0077+000 K0082+000, LAGUNA 3RD LDFlood Control/Hydraulics/Drainage, Roads: Rehabilitation - PCCP | Completed | Laguna 3rd DEO | ₱22.5M |
| 15DI0197 | 10 yrs 9 mo ago | CONSTRUCTION/ REPAIR/ REHABILITATION/ IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - CONCRETING OF FMR, BRGY. DELA PAZ, LAGUNA 1ST L.D.Roads | Completed | Laguna 2nd DEO | ₱16.1M |
| 15DP0104 | 10 yrs 9 mo ago | FLOOD CONTROL PROJECTS BASED ON FLOOD MASTER PLAN FOR METRO MANILA AND SURROUNDING AREAS CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LILIW RIVER, LILIW LAGUNAFlood Control and Drainage | Completed | Laguna 3rd DEO | ₱19.0M |
| 15DP0108 | 10 yrs 9 mo ago | CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM AT BRGY. BANCURO TO STA. LUCIA, BRGY. SILANGAN NAPAPATID, BRGY. MALINAO AND BALINACON, NAGCARLAN, LAGUNAFlood Control and Drainage | Completed | Laguna 3rd DEO | ₱18.4M |
| 25DC0251 | — | REPLACEMENT, RECONSTRUCTION, REHABILITATION, AND/OR REPAIR OF SCHOOL BUILDINGS AND FACILITIES UNDER THE QUICK RESPONSE FUND (QRF), REPAIR/REHABILITATION OF SCHOOL BUILDING, MATAAS NA KAHOY SENIOR HIGH SCHOOL, MATAAS NA KAHOY, BATANGASTrust Funds 2024 | Not Yet Started | Batangas 3rd DEO | ₱2.3M |
| 26DH0032 | — | CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING/VAWC HALL & EVACUATION CENTER), BRGY. SAN DIEGO, LUISIANA, LAGUNA (14.183054, 121.507457)GAA 2026 SSP | Not Yet Started | Laguna 1st DEO | ₱4.8M |
| 26OD0007 | — | REHABILITATION OF ROAD AND DRAINAGE ALONG ROAD 1 (C0+000 TO C0+120), BARANGAY MARULAS, VALENZUELA CITYGAA 2026 SSP | Not Yet Started | Metro Manila 3rd DEO | ₱6.7M |
| 26OD0057 | — | REHABILITATION OF ROAD AND DRAINAGE ALONG PIO-VALENZUELA CORNER CONSTANTINO DRIVE (C0+000 TO C0+160), BARANGAY MARULAS, VALENZUELA CITYGAA 2026 SSP | Not Yet Started | Metro Manila 3rd DEO | ₱18.9M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.