W. GOMEZ TRADING AND CONSTRUCTION
Contractor 5498d14fd4459e805ea0
Overview
PhilGEPS awards
₱621.0M · 81 awards
DPWH contracts
₱582.6M · 63 contracts
Rank by recorded value
#2,193 of 23,487
More info
First record
May 29, 2019 (7 yrs 5 mo ago)
Latest record
Jul 15, 2025 (1 yr 4 mo ago)
DPWH contractor code
39250
Where they work
Latest 25 from a total of 63 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 19OB0292 | 7 yrs 2 mo ago | CONSTRUCTION/REHABILITATION OF B.G. MOLINA MULTI-PURPOSE BUILDING, BRGY. PARANG, MARIKINA CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱9.6M |
| 19OB0440 | 7 yrs 2 mo ago | CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDINGS INCLUDING SITE DEVELOPMENT, BRGY. PARANG, MARIKINA CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱9.6M |
| 19CC0137 | 7 yrs 3 mo ago | CONSTRUCTION OF ROAD WITH DRAINAGE BRGY. BINANG 2ND, BOCAUE, BULACANRoads | Completed | Bulacan 1st DEO | ₱1.9M |
| 19OB0054 | 7 yrs 3 mo ago | CONSTRUCTION/REHABILITATION (EXTENSION) OF MULTI-PURPOSE BUILDING INCLUDING UPGRADING OF FACILITIES WITH GROUND IMPROVEMENT AT BARANGAY HULO (PEOPLES LYING IN) MANDALUYONG CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱4.8M |
| 19OB0303 | 7 yrs 4 mo ago | REHABILITATION OF DRAINAGE SYSTEM INCLUDING CURBS AND GUTTER/SIDEWALK ALONG ORTIGAS AVENUE EXTENSION, PASIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱4.6M |
| 19OB0342 | 7 yrs 4 mo ago | REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. PALATIW, PASIG CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱2.9M |
| 19OB0343 | 7 yrs 4 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. PALATIW, PASIG CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱6.7M |
| 19OB0152 | 7 yrs 4 mo ago | CONSTRUCTION OF ROADS AND DRAINAGE SYSTEM AT CAPISTRANO ST., BRGY. HAGONOY, TAGUIG CITYRoads | Completed | Metro Manila 1st DEO | ₱933.4K |
| 19OB0193 | 7 yrs 4 mo ago | IMPROVEMENT/OVERLAY OF BARANGAY ROADS AT BARANGAY NORTH SIGNAL, TAGUIG CITYRoads | Completed | Metro Manila 1st DEO | ₱2.4M |
| 19OB0042 | 7 yrs 5 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, NAHA IV, BRGY. MANGGAHAN, PASIG CITYBuildings and Facilities | Terminated | Metro Manila 1st DEO | ₱0 |
| 19OB0144 | 7 yrs 5 mo ago | REHABILITATION OF MULTI-PURPOSE BUILDING AT BRGY. TABACALERA, PATEROS, METRO MANILABuildings and Facilities | Completed | Metro Manila 1st DEO | ₱958.7K |
| 19OB0155 | 7 yrs 5 mo ago | CONSTRUCTION OF ROADS AND DRAINAGE SYSTEM AT GUTIERREZ ST., BRGY. BAGUMBAYAN, TAGUIG CITYRoads | Completed | Metro Manila 1st DEO | ₱938.6K |
| 26OB0029 | — | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) NEAR FABELLA ROAD AT BARANGAY MAUWAY, CITY OF MANDALUYONG, 14.579238, 121.039325GAA 2026 SSP | Not Yet Started | Metro Manila 1st DEO | ₱9.4M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.