FY2026 GAA: ₱6.79T
PisoScan

L.M.G. CONSTRUCTION INCORPORATED (FORMERLY: LMG CONSTRUCTION)

Contractor 8389a5e308df89c726ca

Overview

PhilGEPS awards
₱497.0M · 32 awards
DPWH contracts
₱3.71B · 167 contracts
Rank by recorded value
#781 of 23,487

More info

First record
Jan 13, 2016 (10 yrs 10 mo ago)
Latest record
Apr 24, 2025 (1 yr 6 mo ago)
DPWH contractor code
5719

Where they work

Latest 25 from a total of 167 DPWH contracts
Contract IDStartDescriptionStatusOfficeAmount
18OB03368 yrs 7 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY GOVERNMENT EXECUTIVE LOUNGE, CITY GOVERNMENT CENTER, BRGY. CORAZON DE JESUS, SAN JUAN CITYBuildings and FacilitiesCompletedMetro Manila 1st DEO₱9.6M
18DB01018 yrs 7 mo agoCONSTRUCTION OF CANALS AND SLOPE PROTECTION OF BRGY. TULO, NPTI REGIONAL TRAINING CENTER, TAAL, BATANGASFlood Control and DrainageCompletedBatangas 1st DEO₱24.5M
18OI00288 yrs 7 mo agoCONSTRUCTION OF SLOPE PROTECTION STRUCTURES AND OTHER IMPROVEMENT ALONG PASONG COBRA CREEK, LAS PINAFlood Control and DrainageCompletedLas Piñas-Muntinlupa DEO₱23.1M
18OI00308 yrs 7 mo agoRETROFITTING/STRENGTHENING OF PERMANENT BRIDGE: ALABANG-BAYANAN BR.(B01808LZ) ALONG ALABANG-MUNTINLUBridgesCompletedLas Piñas-Muntinlupa DEO₱9.4M
18OI00318 yrs 7 mo agoRETROFITTING/STRENGTHENING OF PERMANENT BRIDGE: LOWER BULI BR. (B01824LZ) ALONG PPTA ROAD, MUNTINLUPBridgesCompletedLas Piñas-Muntinlupa DEO₱9.4M
18OI00328 yrs 7 mo agoRETROFITTING/STRENGTHENING OF PERMANENT BRIDGE: CUPANG BR. (B01825LZ) ALONG PPTA ROAD, MUNTINLUPA CIBridgesCompletedLas Piñas-Muntinlupa DEO₱24.9M
18OI00198 yrs 7 mo agoCONSTRUCTION AND DESILTING OF CREEK, VICTORIA HOMES (BACK OF VICTORIA HOMES ELEMENTARY SCHOOL), BRGYFlood Control and DrainageCompletedLas Piñas-Muntinlupa DEO₱18.5M
18OB03268 yrs 8 mo agoCONSTRUCTION OF MULTI-PURPOSE BLDG. (HALL), BRGY. KABAYANAN, SAN JUAN CITYBuildings and FacilitiesCompletedMetro Manila 1st DEO₱24.0M
18OB03278 yrs 8 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BALONG BATO, SAN JUAN CITYBuildings and FacilitiesCompletedMetro Manila 1st DEO₱24.0M
18OB03328 yrs 8 mo agoREHABILITATION/IMPROVEMENT/UPGRADING OF ROADS, F. MANALO AND F. BLUMENTRITT STREETS, KABAYANAN, SAN JUAN CITYRoadsCompletedMetro Manila 1st DEO₱15.0M
18OB03338 yrs 8 mo agoREHABILITATION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT, AGORA PLAZA, SAN JUAN CITYBuildings and FacilitiesCompletedMetro Manila 1st DEO₱14.4M
18OB03358 yrs 8 mo agoCONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDINGS, BARANGAY CORAZON DE JESUS, SAN JUAN CITYBuildings and FacilitiesCompletedMetro Manila 1st DEO₱9.6M
18OB03218 yrs 8 mo agoCONSTRUCTION OF MULTI-PURPOSE BUILDING, (COVERED COURT) BRGY. BALONG BATO, SAN JUAN CITYBuildings and FacilitiesCompletedMetro Manila 1st DEO₱33.6M
18OG00588 yrs 8 mo agoIMPROVEMENT/ CONSTRUCTION OF ROAD NETWORK AT CAMP AGUINALDO, QUEZON CITYRoadsCompletedQuezon City 2nd DEO₱49.0M
18CK00338 yrs 8 mo agoCONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES - MARANAO BRIDGE (BO3306LZ), ALONG CONCEPCION-LAPAZ ROAD, LAPAZ, TARLACBridgesCompletedTarlac 2nd DEO₱11.7M
18OF01278 yrs 8 mo agoPREVENTIVE MAINTENANCE OF COMMONWEALTH AVE, K0014+404 - K0013+000, Q.C.RoadsCompletedQuezon City 1st DEO₱21.2M
17OI01568 yrs 8 mo agoREHABILITATION OF ROAD OF FRUTO SANTOS AVENUERoadsCompletedLas Piñas-Muntinlupa DEO₱48.1M
18OC00498 yrs 8 mo agoCONSTRUCTION OF BOX CULVERT ALONG DON BOSCO CREEK (FROM RUSSIA ST. TO F. SERRANO ELEMENTARY SCHOOL), BARANGAY DON BOSCO,PARAÑAQUE CITY, METRO MANILAFlood Control and DrainageCompletedMetro Manila 2nd DEO₱27.6M
17OI01288 yrs 8 mo agoCONSTRUCTION OF REINFORCED CONCRETE WALL INCLUDING BRIDGE ALONG ZAPOTE RIVER TALON 5, LAS PINAS CITYFlood Control and DrainageCompletedLas Piñas-Muntinlupa DEO₱22.8M
17OI01398 yrs 8 mo agoCONST. OF SLOPE PROTECTION STRUCTURES & IMPVT ALONG SIN NOMBRE CREEK, LAS PINAS CITYFlood Control and DrainageCompletedLas Piñas-Muntinlupa DEO₱18.4M
18OB00638 yrs 8 mo agoCONSTRUCTION OF NAPINDAN RIVER DRAINAGE OUTFALL INCLUDING LATERALS, BRGY. NAPINDAN,TAGUIG CITYFlood Control and DrainageCompletedMetro Manila 1st DEO₱14.6M
18OB01388 yrs 8 mo agoCONSTRUCTION OF DRAINAGE OUTFALL INCLUDING LATERALS AT BRGY. STA. ANA, PATEROS, TAGUIG CITYFlood Control and DrainageCompletedMetro Manila 1st DEO₱18.3M
18OB01408 yrs 8 mo agoCONSTRUCTION OF DRAINAGE OUTFALL AND LATERALS, BRGY. STO. ROSARIO SILANGAN, PATEROS, METRO MANILAFlood Control and DrainageCompletedMetro Manila 1st DEO₱18.3M
18OB02198 yrs 8 mo agoCONSTRUCTION OF SLOPE PROTECTION AT DAANG KALABAW CREEK AT HAGONOY, TAGUIG CITYFlood Control and DrainageCompletedMetro Manila 1st DEO₱16.0M
18CK00068 yrs 9 mo agoBRIDGE-RETROFITTING/STRENGTHENIG OF PERMANENT BRIDGES: ANUPUL BRIDGE ALONG MNR, BAMBAN, TARLACBridgesCompletedTarlac 2nd DEO₱9.9M