Skip to content
FY2026 GAA: ₱6.79T
PisoScan

A.C. RIVERO DEVELOPMENT CORPORATION

Contractor 8ea8654c349bebee4952

Overview

PhilGEPS awards
₱27.79B · 1,115 awards
DPWH contracts
₱22.42B · 745 contracts
Rank by recorded value
#36 of 23,487

More info

First record
Jan 6, 2012 (14 yrs 10 mo ago)
Latest record
Sep 23, 2026 (1 mo ago)
DPWH contractor code
5122

Where they work

Leyte₱5.35B
Masbate₱2.29B
Latest 25 from a total of 745 DPWH contracts
Contract IDStartDescriptionStatusOfficeAmount
20GB00835 yrs 11 mo agoCONSTRUCTION/CONCRETING OF PANGALCAGAN-BABANGAN ROAD, BUGASONG, ANTIQUERoadsCompletedAntique DEO₱14.1M
20GO00075 yrs 11 mo agoCONSTRUCTION OF REVETMENT WITH FLOODWALL ALONG LUPIT RIVER, PHASE 4, BACOLOD CITYFlood Control and DrainageCompletedBacolod City DEO₱27.0M
20GO00195 yrs 11 mo agoOFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONSTRUCTION ALONG BACOLOD SOUTH ROAD - K0001+160-K0004+085,K0005 + (-915) - K0005+298RoadsCompletedBacolod City DEO₱32.2M
20GO00215 yrs 11 mo agoOFF-CARRIAGEWAY IMPROVEMENT : SHOULDER PAVING/ CONSTRUCTION ALONG BACOLOD CITY BOUNDARY RD.-K0010+387-K0012+047,K0013+108-K0014+401RoadsCompletedBacolod City DEO₱42.2M
20FN00765 yrs 11 mo agoCONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECT FLOOD CONTROL STRUCTURES/FACILITIES CONSTRUCTION OF SAN ROQUE MADAWON FLOOD CONTROL, BRGY. SAN ROQUE MADAWON, NABUA, CAMARINES SURFlood Control and DrainageCompletedCamarines Sur 5th DEO₱47.0M
20GL00696 yrs agoCONSTRUCTION OF DAY CARE CENTER, BRGY. CABADIANGAN , HIMAMAYLAN CITY, NEGROS OCCIDENTALBuildings and FacilitiesCompletedNegros Occidental 2nd DEO₱798.0K
20IF00826 yrs agoCONSTRUCTION AND/OR REPAIR/ REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. MARVEL, ISABEL, LEYTEBuildings and FacilitiesCompletedLeyte 4th DEO₱4.7M
20IF00766 yrs 1 mo agoCONCRETING OF ROAD, ZONE 5, BRGY. LONOY, KANANGA, LEYTERoadsCompletedLeyte 4th DEO₱4.7M
20F000766 yrs 1 mo agoOO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, TAGKAWAYAN-LABO DIVERSION ROAD,(LABO SECTION), CAMARINES NORTE, LABO, CAMARINES NORTE 1ST LEGISLATIVE DISTRICTBridgesCompletedRegion V₱120.4M
20IF01436 yrs 1 mo agoCONSTRUCTION OF ACCESS ROAD, NATIONAL HIGHWAY LEADING TO MERIDA MUNICIPAL HALL, MERIDA, LEYTERoadsCompletedLeyte 4th DEO₱9.6M
20IF01446 yrs 1 mo agoROAD CONCRETING OF BRGY, MAHAYAG BOUNDARY TO BRGY. ANISLAG, ISABEL, LEYTERoadsCompletedLeyte 4th DEO₱9.6M
19G001096 yrs 1 mo agoBACOLOD NEGROS OCCIDENTAL ECONOMIC HIGHWAY (BANOCEH), SEGMENT 3, INCLUDING ROW, BACOLOD CITYRoadsOn-GoingRegion VI₱85.3M
20IL01806 yrs 2 mo agoLOCAL - NATIONAL ROADS AND BRIDGES - LOCAL ROADS, LOCAL INFRASTRUCTURE PROGRAM, CONSTRUCTION / CONCRETING OF ACCESS ROAD LEADING TO MUNICIPAL PORT, SAN FRANCISCO, SOUTHERN LEYTERoadsCompletedSouthern Leyte 1st DEO₱5.0M
20IF00596 yrs 3 mo agoCY 2020 BEFF - CONSTRUCTION OF CLASSROOMS, CANGCOSME ELEMENTARY SCHOOL, PALOMPON, LEYTEBuildings and FacilitiesCompletedLeyte 4th DEO₱3.9M
20IF00666 yrs 3 mo agoCY 2020 BEFF - CONSTRUCTION OF CLASSROOMS, BATCH 2, LOMONON ELEMENTARY SCHOOL, PALOMPON, LEYTEBuildings and FacilitiesCompletedLeyte 4th DEO₱4.1M
20IL01896 yrs 3 mo agoCONCRETING OF HINGATUNGAN TO SITIO GUMAMELA FMR, SILAGO, SOUTHERN LEYTERoadsCompletedSouthern Leyte 1st DEO₱11.9M
20IF00986 yrs 3 mo agoCONCRETING OF BRGY. CABALIWAN FMR (PHASE II) MERIDA, LEYTERoadsCompletedLeyte 4th DEO₱12.3M
20F000486 yrs 4 mo agoOO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, PRIMARY ROADS DAANG MAHARLIKA (LZ),K0356+076-K0357+377.00; K0357+406-K0357+894.00; K0357+920.00-K0358+819.00, CAMARINES NORTE 2ND LEGISLATIVE DISTRICTRoadsCompletedRegion V₱144.8M
20IF01256 yrs 5 mo agoCONSTRUCTION OF RAIN WATER COLLECTORS IN PUBLIC FACILITIES, MATAG-OB CENTRAL SCHOOL, MATAG-OB, LEYTEWater Provision and StorageCompletedLeyte 4th DEO₱216.7K
20IF01266 yrs 5 mo agoCONSTRUCTION OF RAIN WATER COLLECTORS IN PUBLIC FACILITIES, MANSALIP ELEMENTARY SCHOOL, BRGY. MANSALIP, MATAG-OB, LEYTEWater Provision and StorageCompletedLeyte 4th DEO₱216.7K
20IF01276 yrs 5 mo agoCONSTRUCTION OF RAIN WATER COLLECTORS IN PUBLIC FACILITIES, STO. ROSARIO ELEMENTARY SCHOOL, BRGY. STO. ROSARIO, MATAG-OB, LEYTEWater Provision and StorageCompletedLeyte 4th DEO₱216.8K
20IF01286 yrs 5 mo agoCONSTRUCTION OF RAIN WATER COLLECTORS IN PUBLIC FACILITIES, APALE ELEMENTARY SCHOOL, BRGY. APALE, ISABEL, LEYTEWater Provision and StorageCompletedLeyte 4th DEO₱216.2K
20IF01296 yrs 5 mo agoCONSTRUCTION OF RAIN WATER COLLECTORS IN PUBLIC FACILITIES, BINOG ELEMENTARY SCHOOL, BRGY. BINOG, ISABEL, LEYTEWater Provision and StorageCompletedLeyte 4th DEO₱216.2K
20IF01306 yrs 5 mo agoCONSTRUCTION OF RAIN WATER COLLECTORS IN PUBLIC FACILITIES, SAN MIGUEL ELEMENTARY SCHOOL, BRGY. SAN MIGUEL, PALOMPON, LEYTEWater Provision and StorageCompletedLeyte 4th DEO₱216.8K
20IF01316 yrs 5 mo agoCONSTRUCTION OF RAIN WATER COLLECTORS IN PUBLIC FACILITIES, TABUNOK ELEMENTARY SCHOOL, BRGY. TABUNOK, PALOMPON, LEYTEWater Provision and StorageCompletedLeyte 4th DEO₱216.7K