PhilGEPS awards
₱6.28B · 188 awards
DPWH contracts
₱4.82B · 148 contracts
Rank by recorded value
#300 of 23,487
More info
First record
Jan 13, 2016 (10 yrs 10 mo ago)
Latest record
May 20, 2025 (1 yr 5 mo ago)
DPWH contractor code
8931
Where they work
Latest 25 from a total of 148 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 18OB0296 | 8 yrs 4 mo ago | CONSTRUCTION OF RCBC ALONG TAÑONG CREEK, BRGY. TAÑONG, MARIKINA CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱9.2M |
| 18DO0101 | 8 yrs 5 mo ago | ORGANIZATIONAL OUTCOME 2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG UPPER MARIKINA RIVER, SAN MATEOFlood Control and Drainage | Completed | Rizal 2nd DEO | ₱28.2M |
| 18OB0390 | 8 yrs 5 mo ago | INSTALLATION OF FLOODGATES ALONG SAN JUAN RIVER, SAN JUAN CITYFlood Control: Construction - Drainage (e.g., Closed and Open Conduits, Spillway), Flood Control: Construction - Gates | Completed | Metro Manila 1st DEO | ₱4.8M |
| 18OB0345 | 8 yrs 7 mo ago | REHABILITATION OF ROAD NETWORK INCLUDING DRAINAGE AT BRGY. TUMANA, MARIKINA CITYRoads | Completed | Metro Manila 1st DEO | ₱18.8M |
| 18OB0284 | 8 yrs 7 mo ago | REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. SUMILANG, PASIG CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱1.9M |
| 18OB0132 | 8 yrs 8 mo ago | REHABILITATION OF ROADS IN THE VICINITY OF BRGY. ONSE, SAN JUAN CITYRoads | Completed | Metro Manila 1st DEO | ₱2.8M |
| 18OB0283 | 8 yrs 8 mo ago | REHABILITATION OF MULTI-PURPOSE BUILDING AT SOLDIERS VILLAGE, BRGY. STA. LUCIA, PASIG CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱1.9M |
| 18OB0285 | 8 yrs 8 mo ago | REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. BUTING, PASIG CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱1.9M |
| 18OB0253 | 8 yrs 8 mo ago | CONSTRUCTION OF SLOPE PROTECTION OF TAGUIG LINEAR PARK/JOGGING LANE ALONG LAGUNA LAKE, TAGUIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱45.8M |
| 18OB0266 | 8 yrs 8 mo ago | IMPROVEMENT OF DRAINAGE SYSTEM, BRGY. NEW LOWER BICUTAN, TAGUIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱9.2M |
| 18OE0050 | 8 yrs 8 mo ago | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-BANK IMPROVEMENT (STEEL SHEET PILE) ESTERO DE NORTH MAYPAJO STA. 0+325.20 TOFlood Control and Drainage | Completed | North Manila DEO | ₱23.3M |
| 18OB0061 | 8 yrs 8 mo ago | REHABILITATION OF ILUGIN CREEK, PASIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱18.3M |
| 18OB0142 | 8 yrs 8 mo ago | CONSTRUCTION/REHABILITATION OF MARIKINA HEIGHTS SLOPE PROTECTION, BRGY. MARIKINA HEIGHTS, MARIKINA CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱18.3M |
| 18OB0147 | 8 yrs 8 mo ago | REHABILITATION OF ROADS, BRGY. ONSE AND VICINITY, SAN JUAN CITYRoads | Completed | Metro Manila 1st DEO | ₱11.3M |
| 18OB0227 | 8 yrs 8 mo ago | IMPROVEMENT OF DRAINAGE SYSTEM, BRGY. NAPINDAN, TAGUIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱7.3M |
| 18OB0103 | 8 yrs 9 mo ago | CONSTRUCTION OF 3-STOREY MULTI-PURPOSE BUILDING, DAMAYAN, BRGY. MAYBUNGA, PASIG CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱2.7M |
| 17OB0343 | 9 yrs 2 mo ago | REHABILITATION/IMPROVEMENT OF DRAINAGE SYSTEM ALONG VELOSO, DIWA AND ASIÑAS STS., BRGY. SALAPAN, SAN JUAN CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱18.6M |
| 17OB0121 | 9 yrs 4 mo ago | REHABILITATION OF SLOPE PROTECTION OF ILUGIN CREEK, PASIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱36.9M |
| 17OB0286 | 9 yrs 4 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE I), BRGY. SAN ROQUE, PATEROS, PATEROS-TAGUIG CITYBuildings and Facilities | Completed | Metro Manila 1st DEO | ₱9.5M |
| 17OB0287 | 9 yrs 4 mo ago | CONSTRUCTION OF SLOPE PROTECTION ALONG CHAMPACA CREEK, BRGY. FORTUNE, MARIKINA CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱9.3M |
| 17OB0258 | 9 yrs 5 mo ago | REHABILITATION/DESILTING OF BULI CREEK, BRGY. ST. LUCIA, PASIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱7.4M |
| 17OB0129 | 9 yrs 7 mo ago | REHABILITATION OF MANGGAHAN FLOODWAY DRAINAGE OUTFALL ALONG EAST BANK ROAD, PASIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱13.9M |
| 17OB0094 | 9 yrs 8 mo ago | IMPROVEMENT OF CREEK BED, MAHABANG ILOG CREEK, BRGY. MAYBUNGA AND BRGY. SAN MIGUEL, PASIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱17.6M |
| 17OB0089 | 9 yrs 9 mo ago | CONSTRUCTION OF J. P. RIZAL DRAINAGE OUTFALL INCLUDING LATERALS, BRGY. STO. NIÑO, MARIKINA CITY 1ST LDFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱18.5M |
| 17OB0096 | 9 yrs 9 mo ago | CONSTRUCTION OF M. ALMEDA AND VICINITY DRAINAGE OUTFALL, BRGY. STO. ROSARIO SILANGAN, PATEROS, TAGUIG-PATEROS 1ST LDFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱14.0M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.