DPWH contracts
₱380.4M · 14 contracts
Rank by recorded value
#4,886 of 23,487
More info
First record
Nov 28, 2018 (7 yrs 11 mo ago)
Latest record
Mar 28, 2022 (4 yrs 7 mo ago)
DPWH contractor code
19657
Where they work
Quezon₱380.4M
Latest 14 from a total of 14 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 22DM0129 | 4 yrs 7 mo ago | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS UNISAN DIVERSION ROAD, QUEZONUNISAN, QUEZONGAA 2022 OO-1 | Completed | Quezon 3rd DEO | ₱39.0M |
| 22DM0015 | 4 yrs 8 mo ago | NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS- P BURGOS - POTOTANIN JCT - K0195+123 - K0198+174UNISAN, QUEZONGAA 2022 OO-1 | Completed | Quezon 3rd DEO | ₱58.9M |
| 21DM0056 | 5 yrs 8 mo ago | CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG PIRIS RIVER, BRGY. POBLACION, BUENAVISTA, QUEZONGAA 2021 OO-2 | Completed | Quezon 3rd DEO | ₱96.5M |
| 21DM0039 | 5 yrs 9 mo ago | NETWORK DEVELOPMENT: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - UNISAN DIVERSION ROAD, QUEZON, UNISAN, QUEZONGAA 2021 OO-1 | Completed | Quezon 3rd DEO | ₱49.0M |
| 18DM0111 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO(2)-STOREY FOUR(4)-CLASSROOM SCHOOL BUILDING AT AURORA ES SAN FRANCISCO (AURORA), QUEZONGAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱12.3M |
| 18DM0112 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO(2)-STOREY FOUR(4)-CLASSROOM SCHOOL BUILDING AT DON JUAN VERCELOS ES SAN FRANCISCO (AURORA), QUEZONGAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱12.2M |
| 18DM0117 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING AT TAGBACAN NHS (FORMERLY TAGBACAN ILAYA IS)GAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱11.9M |
| 18DM0121 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING AT SAN ISIDRO NATIONAL HIGH SCHOOLGAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱12.1M |
| 18DM0095 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO(2)-STOREY FOUR(4)-CLASSROOM SCHOOL BUILDING AT CATANAUAN CS CATANAUAN, QUEZONGAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱12.0M |
| 18DM0096 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO(2)-STOREY FOUR(4)-CLASSROOM SCHOOL BUILDING AT DAHICAN ES CATANAUAN, QUEZONGAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱12.0M |
| 18DM0097 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO(2) UNITS TWO(2)-STOREY FOUR(4)-CLASSROOM SCHOOL BUILDING AT SAN ISIDRO ES CANATANUAN, QUEZONGAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱24.2M |
| 18DM0098 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO(2)-STOREY FOUR(4)-CLASSROOM SCHOOL BUILDING AT TAGABAS IBABA ES CATANAUAN, QUEZONGAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱11.9M |
| 18DM0099 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO(2)-STOREY FOUR(4)-CLASSROOM SCHOOL BUILDING AT TAGBACAN IBABA ES CATANUAN, QUEZONGAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱11.9M |
| 18DM0100 | 7 yrs 11 mo ago | CONSTRUCTION OF TWO(2)-STOREY SIX(6)-CLASSROOM SCHOOL BUILDING AT BACONG IBABA ES GENERAL LUNA, QUEZONGAA 2018 DepEd BEFF | Completed | Quezon 3rd DEO | ₱16.5M |