GASAT BUILDERS AND SUPPLIES INC.
Contractor b1d8d22341bf930922a2
Overview
PhilGEPS awards
₱1.40B · 96 awards
DPWH contracts
₱1.04B · 74 contracts
Rank by recorded value
#1,247 of 23,487
More info
First record
May 18, 2022 (4 yrs 6 mo ago)
Latest record
Aug 20, 2026 (2 mos ago)
DPWH contractor code
51666
Where they work
Latest 25 from a total of 74 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 24CN0010 | 2 yrs 8 mo ago | ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, A CASTAÑEDA -- MA AURORA-SN LUIS RD, K0196 + 479 - K0196 + 506, K0198 + 590 - K0198 + 617, K0202 + 520 - K0202 + 544, .........Roads | Completed | Aurora DEO | ₱11.7M |
| 24CL0085 | 2 yrs 8 mo ago | CONSTRUCTION OF LUPANG PANGAKO ROAD, SAN AGUSTINE, IBA, ZAMBALESRoads | Completed | Zambales 1st DEO | ₱14.5M |
| 24CL0032 | 2 yrs 8 mo ago | CONSTRUCTION OF ROAD, PUROK 6, BARANGAY BOLITOK, STA. CRUZ, ZAMBALESRoads | Completed | Zambales 1st DEO | ₱19.3M |
| 24CN0009 | 2 yrs 9 mo ago | ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, NUEVA ECIJA - AURORA RD, K0179 + 630 - K0179 + 696, K0185 + 850 - K0185 + 900, K0189 + 675 - K0189 + 705, K0196 + 280.........GAA 2024 OO-1 | Completed | Aurora DEO | ₱25.3M |
| 24CN0013 | 2 yrs 9 mo ago | NETWORK DEVELOPMENT PROGRAM - OFF - CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS, BALER - CASIGURAN RD (DINADIAWAN - CASIGURAN SECT), K0301 + 388 - K0301 + 645, K0303 + 243 - K0303 + 410, K0316 + 000 - K0316 + 204, K0317 + 021 - K0317 + 028, K0318 + 929 ....GAA 2024 OO-1 | Completed | Aurora DEO | ₱12.1M |
| 23CL0159 | 2 yrs 11 mo ago | CONCRETING OF FELIX ROAD, BRGY. SAN ISIDRO, CABANGAN, ZAMBALESRoads | On-Going | Zambales 1st DEO | ₱23.6M |
| 23CL0149 | 3 yrs 3 mo ago | CONCRETING OF SITIO COMBUAN, PUROK 1-A, PUROK 1-B AND PUROK 4, BRGY. BATONLAPOC FMR, BRGY. BATONLAPOC, BOTOLAN, ZAMBALESRoads | Completed | Zambales 1st DEO | ₱19.5M |
| 23CL0147 | 3 yrs 3 mo ago | CONSTRUCTION OF FISHERMAN'S WHARF/CAUSEWAY, BRGY. SAN SALVADOR, MASINLOC, ZAMBALESGAA 2023 CSSP | On-Going | Zambales 1st DEO | ₱9.6M |
| 23CL0139 | 3 yrs 5 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN'S OFFICE), BRGY. PAMONORAN, STA. CRUZ, ZAMBALESBuildings and Facilities | Completed | Zambales 1st DEO | ₱4.9M |
| 23CL0140 | 3 yrs 5 mo ago | CONSTRUCTION OF DR. FLORENTINO DOBLE MEMORIAL HOSPITAL, PHASE 4, BRGY. TAUGTOG, BOTOLAN, ZAMBALESBuildings and Facilities | Completed | Zambales 1st DEO | ₱19.6M |
| 23CL0131 | 3 yrs 5 mo ago | CONSTRUCTION OF DRAINAGE SYSTEM, MAESTRE ST., BRGY. POBLACION, STA. CRUZ, ZAMBALESFlood Control and Drainage | Completed | Zambales 1st DEO | ₱19.3M |
| 23CL0136 | 3 yrs 5 mo ago | COMPLETION OF MULTI-PURPOSE BUILDING (IBA MUNICIPAL HALL), IBA, ZAMBALES (PHASE III)Buildings and Facilities | Completed | Zambales 1st DEO | ₱19.5M |
| 23CL0088 | 3 yrs 5 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT DR. FLORENTINO DOBLE MEMORIAL HOSPITAL, BARANGAY TAUGTOG, BOTOLAN, ZAMBALESBuildings and Facilities | Completed | Zambales 1st DEO | ₱9.8M |
| 23CL0124 | 3 yrs 5 mo ago | CONSTRUCTION OF ROAD, SITIO TAMBAK GOING TO GOVIC HIGHWAY, PALANGINAN, IBA, ZAMBALESRoads | Completed | Zambales 1st DEO | ₱19.4M |
| 23CL0132 | 3 yrs 5 mo ago | CONSTRUCTION OF ROAD AT PUROK 3, (TONGSON AREA) LUCAPON NORTH, STA. CRUZ, ZAMBALESRoads | Completed | Zambales 1st DEO | ₱5.9M |
| 23CL0110 | 3 yrs 6 mo ago | CONSTRUCTION OF ROADS, BRGY. MALOMA, SAN FELIPE, ZAMBALESRoads | Completed | Zambales 1st DEO | ₱9.6M |
| 23CL0111 | 3 yrs 6 mo ago | CONSTRUCTION OF STO. ROSARIO COVERED COURT, BRGY. STO. ROSARIO, IBA, ZAMBALESBuildings and Facilities | Completed | Zambales 1st DEO | ₱9.6M |
| 23CN0082 | 3 yrs 6 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMMAND CENTER), BALER, AURORABuildings and Facilities | Completed | Aurora DEO | ₱29.1M |
| 23CN0010 | 3 yrs 7 mo ago | ASSET PRESERVATION PROGRMAM - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS, BALER-CASIGURAN RD (DINADIAWAN-CASIGURAN SECT) - K0305+560 - K0306+117, K0312+160 - K0312+890Roads | Completed | Aurora DEO | ₱25.3M |
| 23CN0162 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DIANAWAN ELEMENTARY SCHOOL, BRGY. DIANAWAN, MARIA AURORA, AURORABuildings and Facilities | Completed | Aurora DEO | ₱4.9M |
| 23BC0011 | 3 yrs 9 mo ago | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-BRIDGE PROGRAM-WIDENING OF PERMANENT BRIDGES-CABALLEBAAN BR. (B01016LZ) ALONG MANILA NORTH RD, PAMPLONA, CAGAYANBridges | Completed | Cagayan 2nd DEO | ₱25.5M |
| 22CN0023 | 4 yrs 5 mo ago | NETWORK DEVELOPMENT PROGRAM - OFF - CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS, BALER - CASIGURAN RD (DINADIAWAN - CASIGURAN SECT), K0339 + 275 - K0339 + 431, K0339 + 606 - K0340 + 023, K0340 + 845 - K0342 + 292Roads | Completed | Aurora DEO | ₱13.0M |
| 26BC0009 | — | OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TERTIARY ROAD -JCT. LOGAC-LASAM-GAGABUTAN ROAD (S00656LZ) CHAINAGE 17045-CHAINAGE 17115GAA 2026 OO-1 | Not Yet Started | Cagayan 2nd DEO | ₱13.4M |
| 26BC0011 | — | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TERTIARY ROADOF TERTIARY ROAD-JCT. LOGAC-LASAM-GAGABUTAN ROAD (S00656LZ) CHGAA 2026 OO-1 | Not Yet Started | Cagayan 2nd DEO | ₱22.3M |