| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 24CC0597 | 1 yr 10 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, PACKAGE B, PUROK 4, BARANGAY PULONG GUBAT, BALAGTAS, BULACANFlood Control and Drainage | On-Going | Bulacan 1st DEO | ₱96.5M |
| 24OF0263 | 1 yr 10 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT FILINVEST, BARANGAY BAGONGSILANGAN, QUEZON CITYFlood Control and Drainage | On-Going | Quezon City 1st DEO | ₱143.3M |
| 24CC0598 | 1 yr 10 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER (TRIBUTARY), PACKAGE D), PUROK 5, BARANGAY BULIHAN, PLARIDEL, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱96.5M |
| 24CC0599 | 1 yr 10 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG GUIGUINTO RIVER (TRIBUTARY), PACKAGE G, PUROK 4, BARANGAY BAGONG SILANG, PLARIDEL, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱96.5M |
| 24CC0600 | 1 yr 10 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER (TRIBUTARY), PACKAGE G, PUROK 4, BARANGAY SAN JOSE, PLARIDEL, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱96.5M |
| 24CC0573 | 1 yr 11 mo ago | CONSTRUCTION OF RIVER WALL ALONG ANGAT RIVER, PACKAGE A, BARANGAY TANAWAN, BUSTOS, BULACANFlood Control and Drainage | On-Going | Bulacan 1st DEO | ₱92.6M |
| 24CC0574 | 1 yr 11 mo ago | CONSTRUCTION OF RIVER WALL ALONG ANGAT RIVER, PACKAGE B, BARANGAY TANAWAN, BUSTOS, BULACANFlood Control and Drainage | On-Going | Bulacan 1st DEO | ₱92.7M |
| 24CC0575 | 1 yr 11 mo ago | CONSTRUCTION OF RIVER WALL ALONG ANGAT RIVER, PACKAGE C, BARANGAY TANAWAN, BUSTOS, BULACANFlood Control and Drainage | On-Going | Bulacan 1st DEO | ₱92.7M |
| 24OD0306 | 1 yr 11 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG THE BANKS OF PH10 CREEK, BARANGAY 176, CALOOCAN CITYFlood Control and Drainage | Completed | Metro Manila 3rd DEO | ₱94.8M |
| 24OB0302 | 2 yrs 5 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING, J. RIZAL STREET, BARANGAY MABINI J. RIZAL, MANDALUYONG CITYGAA 2024 SSP | On-Going | Metro Manila 1st DEO | ₱53.6M |
| 24CC0421 | 2 yrs 6 mo ago | CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, SAN JOSE SECTION, PLARIDEL, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱77.2M |
| 24CC0422 | 2 yrs 6 mo ago | CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, BINTOG SECTION, PLARIDEL, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱77.2M |
| 24DN0111 | 2 yrs 6 mo ago | CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - MANILA EAST ROAD - K0030+589 - K0032+146 RIZAL (FIRST DISTRICT)Roads | On-Going | Rizal 1st DEO | ₱41.1M |
| 24CC0381 | 2 yrs 6 mo ago | CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, CAMBAOG SECTION, BUSTOS, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱77.2M |
| 24CC0383 | 2 yrs 6 mo ago | CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, LUMANG BAYAN SECTION, PLARIDEL, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱77.2M |
| 24CC0396 | 2 yrs 6 mo ago | CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE ALONG ANAGT RIVER, CULIANIN SECTION (PUROK 2), PLARIDEL, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱77.2M |
| 24CC0293 | 2 yrs 7 mo ago | CONSTRUCTION OF REINFORCED CONCRETE FLOOD CONTROL STRUCTURE, BARANGAY CAMBAOG (SITIO TEODORO), BUSTOS, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱77.2M |
| 24OB0088 | 2 yrs 7 mo ago | REHABILITATION OF SAPANG MALAPIT CREEK, PASIG CITYFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱16.3M |
| 24CC0216 | 2 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (LOLOMBOY NATIONAL HIGH SCHOOL), LOLOMBOY, BOCAUE, BULACANBuildings and Facilities | On-Going | Bulacan 1st DEO | ₱59.4M |
| 24CC0204 | 2 yrs 8 mo ago | CONSTRUCTION OF ROAD, BARANGAY TAAL, BOCAUE, BULACANRoads | Completed | Bulacan 1st DEO | ₱4.9M |
| 24E00160 | 2 yrs 8 mo ago | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PHASE 3, BRGY. SAN LUIS, NAUJAN, OR. MINDORGAA 2024 SSP | On-Going | MIMAROPA Region | ₱186.0M |
| 24CC0158 | 2 yrs 8 mo ago | CONSTRUCTION OF RIVER PROTECTION STRUCTURE, BARANGAY STA. CRUZ, GUIGUINTO, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱39.6M |
| 24CC0163 | 2 yrs 8 mo ago | CONSTRUCTION OF RIVER CONTROL STRUCTURE AT BARANGAY PRITIL PUROK 1 TO PUROK 2, GUIGUINTO, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱77.2M |
| 24CC0183 | 2 yrs 8 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER, BARANGAY SAN JUAN, PUROK 4-PUROK 5, BALAGTAS, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱49.5M |
| 24OA0015 | 2 yrs 9 mo ago | CONSTRUCTION OF RIVERWALL ALONG TANGOS RIVER (PHASE 2) NAVOTAS CITYFlood Control and Drainage | Completed | Malabon-Navotas DEO | ₱49.0M |