PhilGEPS awards
₱11.34B · 248 awards
DPWH contracts
₱8.64B · 180 contracts
Rank by recorded value
#147 of 23,487
More info
First record
Mar 18, 2016 (10 yrs 8 mo ago)
Latest record
Dec 8, 2025 (11 mos ago)
DPWH contractor code
34061
Where they work
Latest 25 from a total of 180 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 23CC0062 | 3 yrs 9 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BAGBAG CREEK, PRITIL SECTION, GUIGUINTO, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱49.0M |
| 23CC0063 | 3 yrs 9 mo ago | CONSTRUCTION OF RIVER CONTROL PROJECT ALONG ANGAT RIVER, LUMANG BAYAN SECTION, STA. 03+190 TO STA. 03+340, PLARIDEL, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱29.4M |
| 23CC0119 | 3 yrs 9 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BULACAN STATE UNIVERSITY), POBLACION, BUSTOS, BULACANBuildings and Facilities | Completed | Bulacan 1st DEO | ₱29.7M |
| 22OE0173 | 3 yrs 10 mo ago | REHABILITATION OF OSPITAL NG TONDO, MANILA CITYBuildings and Facilities | Completed | North Manila DEO | ₱48.2M |
| 21CC0297 | 4 yrs ago | CONST./REHAB. OF WATER SUPPLY/SEPTAGE & SEWERAGE/RAINWATER COLLECTOR SYSTEM, EUSEBIO ROQUE ES, REAL DE CACARONG, MAPULANG LUPA ES, MAPULANG LUPA, PINAGKUARTELAN ES, PINAGKUARTELAN, MATIAS B. SALVADOR ES, BAGONG BARRIO, MALIBONG BATA ES, MALIBONG BATA, MASWater Provision and Storage | Completed | Bulacan 1st DEO | ₱4.4M |
| 22DH0066 | 4 yrs 2 mo ago | CONSTRUCTION OF ROAD, SAARAY ROAD TO GALALAN ROAD, BRGY. SARAY, PAKIL, LAGUNARoads | Completed | Laguna 1st DEO | ₱96.5M |
| 22CC0327 | 4 yrs 5 mo ago | PACKAGE 1 - CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE I), LOLOMBOY ELEMENTARY SCHOOL AND CONSTRUCTION OF MULTI-PURPOSE BUILDING (SENIOR CITIZEN BUILDING), AZICATE, LOLOMBOY, BOCAUE, BULACANBuildings and Facilities | Completed | Bulacan 1st DEO | ₱49.5M |
| 22CC0283 | 4 yrs 7 mo ago | CONSTRUCTION OF MUNICIPAL DISASTER RISK REDUCTION MANAGEMENT OFFICE, BRGY. POBLACION, GUIGUINTO, BULACANBuildings and Facilities | Completed | Bulacan 1st DEO | ₱9.9M |
| 22CC0306 | 4 yrs 7 mo ago | CONCRETING/REHABILITATION OF BRGY. MALIBONG MATANDA TO BRGY. BATIA FMR, BRGY. MALIBONG MATANDA, PANDI AND BRGY. BATIA, BOCAUE, BULACANRoads | Completed | Bulacan 1st DEO | ₱14.5M |
| 22CC0086 | 4 yrs 7 mo ago | CONSTRUCTION OF ROAD, DUHAT, BOCAUE, BULACANRoads | Completed | Bulacan 1st DEO | ₱6.9M |
| 22CC0277 | 4 yrs 7 mo ago | CONSTRUCTION OF MANILA NORTH ROAD DRAINAGE TRIBUTARY OUTFALL, LONGOS-CALUMPIT SECTION, MALOLOS CITY, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱47.5M |
| 22CC0216 | 4 yrs 7 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BOCAUE RIVER, STA. 00+398 TO STA. 00+598, BRGY. TAAL, BOCAUE, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱24.5M |
| 22CC0234 | 4 yrs 7 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, STA. 01+120 - STA. 01+270, BRGY. PIEL, BALIUAG, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱25.5M |
| 22OE0062 | 4 yrs 7 mo ago | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - NORTH ANTIPOLO ST CHAINAGE 150.2 TO 288.7Roads | Terminated | North Manila DEO | ₱0 |
| 22CD0181 | 4 yrs 7 mo ago | CONSTRUCTION OF ROAD, BARANGAY PARTIDA, NORZAGARAY, BULACANRoads | Completed | Bulacan 2nd DEO | ₱9.7M |
| 21OD0142 | 4 yrs 7 mo ago | CONSTRUCTION OF FLOOD CONTROL WALL ALONG THE BANKS OF CREEKS IN BRGY. 160, CALOOCAN CITYFlood Control and Drainage | Completed | Metro Manila 3rd DEO | ₱9.5M |
| 22OB0311 | 4 yrs 7 mo ago | BANK IMPROVEMENT OF PATEROS RIVER, PATEROS, METRO MANILAFlood Control and Drainage | Completed | Metro Manila 1st DEO | ₱49.0M |
| 22CC0151 | 4 yrs 8 mo ago | CONSTRUCTION OF ROAD, BARANGAY DUHAT, BOCAUE, BULACANRoads | Completed | Bulacan 1st DEO | ₱4.9M |
| 22CC0232 | 4 yrs 8 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BALAGTAS RIVER (PHASE 2), BARANGAY MALIBONG, PANDI, BULACANFlood Control and Drainage | Completed | Bulacan 1st DEO | ₱59.4M |
| 22OE0077 | 4 yrs 8 mo ago | REHABILITATION OF SCHOOL BUILDING AT CM RECTO HIGH SCHOOL, BARANGAY 412, MANILABuildings and Facilities | Completed | North Manila DEO | ₱4.8M |
| 22OE0081 | 4 yrs 8 mo ago | REHABILITATION OF SCHOOL BUILDING WITHIN BARANGAY 581, ZONE 57, SAMPALOC, MANILABuildings and Facilities | Completed | North Manila DEO | ₱14.8M |
| 22CC0189 | 4 yrs 8 mo ago | CONST./IMP. OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - MATUNGAO-GUIGUINTO PROVINCIAL ROAD CONNECTING MCARTHUR HIGHWAY AND BANTAYAN ROAD IN SUPPORTRoads | Completed | Bulacan 1st DEO | ₱49.7M |
| 22CC0002 | 4 yrs 8 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY BALITE, MALOLOS, BULACANBuildings and Facilities | Completed | Bulacan 1st DEO | ₱4.9M |
| 22CC0112 | 4 yrs 8 mo ago | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LOLOMBOY, BOCAUE, BULACANBuildings and Facilities | Completed | Bulacan 1st DEO | ₱8.9M |
| 22CC0185 | 4 yrs 8 mo ago | NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BUSTOS DIVERSION ROAD, BULACANRoads | On-Going | Bulacan 1st DEO | ₱19.2M |