Overview
PhilGEPS awards
₱11.06B · 60 awards
DPWH contracts
₱0 · 0 contracts
Rank by recorded value
#301 of 23,487
More info
First record
Dec 10, 2010 (15 yrs 11 mo ago)
Latest record
May 15, 2025 (1 yr 6 mo ago)
DPWH contractor code
Not in the DPWH list
Where they work
Latest 25 from a total of 60 awards
| Record ID | Reference | Age | Project title | Procuring entity | Amount |
|---|---|---|---|---|---|
| 0f76cd112a1f… | 5785192 | 7 yrs 9 mo ago | Construction of Talandang Steel Reservoir | DAVAO CITY WATER DISTRICT | ₱80.7M |
| d7d6c1635555… | LFP PLW No. 046-2018 | 7 yrs 10 mo ago | Port of San Fernando, El Nido, Palawan | PHILIPPINE PORTS AUTHORITY - HEAD OFFICE | ₱191.4M |
| 45a4b504fac5… | LFP PLW No. 022-2018 | 8 yrs 1 mo ago | Borac Port, Brgy. Borac, Coron, Palawan | PHILIPPINE PORTS AUTHORITY - HEAD OFFICE | ₱319.9M |
| f1a092af63d9… | 5445030 | 8 yrs 2 mo ago | Construction of Indangan Elevated Steel Tank | DAVAO CITY WATER DISTRICT | ₱53.9M |
| ef5836f12a29… | PCCO-2018-003 | 8 yrs 3 mo ago | Repair/Rehabilitation/Improvement of Facilities at | PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY - MAIN | ₱61.4M |
| 0bdf28ae7db5… | RB-MS-2017-043 | 9 yrs 2 mo ago | DINAHICAN PORT DEVELOPMENT PROJECT | DEPARTMENT OF TRANSPORTATION AND COMMUNICATIONS - MAIN | ₱38.9M |
| 12263b5a8460… | 4541273 | 9 yrs 3 mo ago | Pipelaying of Transmission Line | DAVAO CITY WATER DISTRICT | ₱92.6M |
| 8a4f1f3d4773… | CW-2017-001 | 9 yrs 9 mo ago | Civil Works | BUREAU OF JAIL MANAGEMENT AND PENOLOGY - NHQ | ₱29.4M |
| ab5f85429c76… | 1 | 9 yrs 10 mo ago | CONSTRUCTION OF 500MMØ EPOXY LINED-EPOXY COATED (E | TAGUM WATER DISTRICT | ₱34.4M |
| c66887d49fec… | LFP SSG No. 015-2016 | 9 yrs 11 mo ago | POB,Port of Makar,General Santos City | PHILIPPINE PORTS AUTHORITY - HEAD OFFICE | ₱65.9M |
| 8db6f8d99ead… | CW-2016-0016 | 9 yrs 11 mo ago | civil work | BUREAU OF JAIL MANAGEMENT AND PENOLOGY - NHQ | ₱14.3M |
| f5c44a499188… | 4009485 | 10 yrs ago | PIPELINE IMPROVEMENT | DAVAO CITY WATER DISTRICT | ₱141.4M |
| 8afa8f06c18b… | 30201 | 10 yrs ago | CONSTRUCTION OF 700MMØ EPOXY LINED-EPOXY COATED (E | TAGUM WATER DISTRICT | ₱42.9M |
| 0296a97b1385… | BACB2016-001 | 10 yrs 2 mo ago | CONSTRUCTION OF 700MMØ EPOXY LINED-EPOXY COATED | TAGUM WATER DISTRICT | ₱45.8M |
| aca718ee4a2b… | 3859350 | 10 yrs 3 mo ago | CONSTRUCTION OF RESERVOIR | DAVAO CITY WATER DISTRICT | ₱90.8M |
| 443d0a54eb7a… | 3773729 | 10 yrs 4 mo ago | CONSTRUCTION OF RESERVOIR | DAVAO CITY WATER DISTRICT | ₱14.5M |
| e4372a99bef9… | 3773718 | 10 yrs 4 mo ago | PIPELINE IMPROVEMENT | DAVAO CITY WATER DISTRICT | ₱96.9M |
| 9f20e461f02e… | 3773733 | 10 yrs 4 mo ago | CONSTRUCTION OF RESERVOIR | DAVAO CITY WATER DISTRICT | ₱24.3M |
| 07ff97699715… | LFP PMO SSG No. 039-2015 | 10 yrs 9 mo ago | Port of Makar, General Santos City, South Cotabato | PHILIPPINE PORTS AUTHORITY - HEAD OFFICE | ₱593.9M |
| 993307a0304c… | MABT-16-0209 | 10 yrs 9 mo ago | Civil Works | MUNICIPALITY OF MABALACAT, PAMPANGA | ₱10.0M |
| fffd517d6b8e… | 3356559 | 11 yrs ago | Pipelaying of Distribution Lines | DAVAO CITY WATER DISTRICT | ₱174.8M |
| e309f902861b… | PCG-15-08-0073 | 11 yrs 2 mo ago | Proposed CPCG Building Rear Wall Protection and Co | PHILIPPINE COAST GUARD | ₱1.6M |
| 84456833a826… | LOG MSSP 2015-07-063-CPC | 11 yrs 3 mo ago | S1-B2014-015( rev 1) - Construction of Mooring Fac | NATIONAL POWER CORPORATION | ₱27.9M |
| ac6a37ab1ac7… | LFP PMO PLW No. 015-2015 | 11 yrs 4 mo ago | Port of Puerto Princesa, Palawan | PHILIPPINE PORTS AUTHORITY - HEAD OFFICE | ₱309.4M |
| d9cee274a8a5… | 1410-168-11 | 11 yrs 5 mo ago | Relocation Housing Units and Amenities for the Inf | LIGHT RAIL TRANSIT AUTHORITY | ₱397.9M |
Records are grouped under one contractor when the names match after removing case, punctuation and notes such as "(formerly …)". Different legal names stay separate. PhilGEPS and DPWH figures can overlap, since one DPWH contract can also appear in PhilGEPS.