ROYAL CROWN MONARCH CONSTRUCTION & SUPPLIES CORP.
Contractor fadd4c6b4b7dfa02657b
Overview
PhilGEPS awards
₱28.53B · 466 awards
DPWH contracts
₱25.72B · 385 contracts
Rank by recorded value
#32 of 23,487
More info
First record
Nov 16, 2011 (15 yrs ago)
Latest record
Sep 6, 2025 (1 yr 2 mo ago)
DPWH contractor code
09036
Where they work
Latest 25 from a total of 385 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 25CD0203 | 1 yr 7 mo ago | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS STA MARIA-NORZAGARAY RD - K0036+760 - K0036+991, K0037+000 - K0037+080Roads | On-Going | Bulacan 2nd DEO | ₱9.8M |
| 25CK0001 | 1 yr 7 mo ago | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - ALONG MANILA NORTH ROAD, K0111+ 747 - K0112 + 930, CAPAS, TARLACRoads | Completed | Tarlac 2nd DEO | ₱96.5M |
| 25CK0002 | 1 yr 7 mo ago | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - ALONG MANILA NORTH ROAD, K0112 + 930 - K0114 + 113, CAPAS, TARLACGAA 2025 OO-1 | Completed | Tarlac 2nd DEO | ₱96.5M |
| 25CK0068 | 1 yr 7 mo ago | REHABILITATION OF DIKE ALONG O'DONNELL RIVER, RIGHT BANK OF BARANGAY STA. LUCIA SECTION, SEGMENT B, STA. 2 + 837.75 TO STA. 3 + 119.83, CAPAS, TARLACGAA 2025 OO-2 | Completed | Tarlac 2nd DEO | ₱96.5M |
| 25CJ0008 | 1 yr 7 mo ago | PREVENTIVE MAINTENANCE ROMULO H-WAY - K0126 + 764 - K0127 + 459, K0127 + 625 - K0127 + 711Roads | Completed | Tarlac DEO | ₱50.2M |
| 25CD0046 | 1 yr 8 mo ago | REHABILITATION OF ROAD (PHASE 1), AREA A, BARANGAY MINUYAN, CITY OF SAN JOSE DEL MONTE, BULACANRoads | On-Going | Bulacan 2nd DEO | ₱47.5M |
| 25CD0089 | 1 yr 8 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ANGAT RIVER, POBLACION SECTION, STA. 14+834 STA. 14+922, NORZAGARAY, BULACANFlood Control and Drainage | On-Going | Bulacan 2nd DEO | ₱38.0M |
| 25CJ0045 | 1 yr 8 mo ago | CONSTRUCTION OF PANIQUI DRAINAGE SYSTEM PHASE 2, PANIQUI, TARLACFlood Control and Drainage | On-Going | Tarlac DEO | ₱94.1M |
| 25CJ0055 | 1 yr 8 mo ago | CONSTRUCTION OF PANIQUI DRAINAGE SYSTEM PHASE 3, PANIQUI, TARLACFlood Control and Drainage | On-Going | Tarlac DEO | ₱72.8M |
| 25CG0037 | 1 yr 8 mo ago | ASSET PRESERVATION PROGRAM: CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAKL ROADS - TERTIARY ROADS - OLD MANILA NORTH RD - K0066+ (-449) - K0066+217, K0066+292 - K0067+217Roads | Completed | Pampanga 1st DEO | ₱36.6M |
| 25CD0082 | 1 yr 8 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER AND ITS TRIBUTARIES, CAINGIN - MEYLAND SECTION, STA. 9+613 - STA. 9+850, MEYCAUAYAN CITY, BULACANGAA 2025 OO-2 | Completed | Bulacan 2nd DEO | ₱96.5M |
| 25CD0020 | 1 yr 8 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, SAN JOSE RIVER RIVER, SAN JOSE DEL MONTE CITY, BULACANGAA 2025 OO-2 | Completed | Bulacan 2nd DEO | ₱96.5M |
| 25CD0021 | 1 yr 8 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG NCR/BULACAN BDRY. - BIGTE - IPO DAM ROAD, SAN JOSE RIVER, SAN JOSE DEL MONTE CITY, BULACANGAA 2025 OO-2 | Completed | Bulacan 2nd DEO | ₱96.5M |
| 25CG0041 | 1 yr 8 mo ago | NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ARAYAT - MAGALANG BY-PASS ROAD, PAMPANGAGAA 2025 OO-1 | Completed | Pampanga 1st DEO | ₱93.6M |
| 25CK0029 | 1 yr 8 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BINABAKOD RIVER (LEFT AND RIGHT BANK), DOWNSTREAM OF CHECK GATE, LA PAZ, TARLACFlood Control and Drainage | Completed | Tarlac 2nd DEO | ₱96.5M |
| 25CJ0027 | 1 yr 9 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BAKET-BAKET RIVER (SEGMENT 12), MONCADA, TARLACFlood Control and Drainage | Completed | Tarlac DEO | ₱96.5M |
| 25CJ0038 | 1 yr 9 mo ago | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INERANGAN RIVER, SEGMENT 14, RAMOS, TARLACFlood Control and Drainage | Completed | Tarlac DEO | ₱70.2M |
| 24CG0329 | 1 yr 10 mo ago | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 1, BARANGAY LACQUIOS, ARAYAT, PAMPANGAUnprogrammed Appropriations 2024 | On-Going | Pampanga 1st DEO | ₱140.4M |
| 24CG0330 | 1 yr 10 mo ago | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 2, BARANGAY LACQUIOS, ARAYAT, PAMPANGAUnprogrammed Appropriations 2024 | On-Going | Pampanga 1st DEO | ₱140.4M |
| 24CG0331 | 1 yr 10 mo ago | FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PAMPANGA RIVER BANK, PHASE 3, BARANGAY LACQUIOS, ARAYAT, PAMPANGAUnprogrammed Appropriations 2024 | On-Going | Pampanga 1st DEO | ₱140.4M |
| 24CJ0365 | 1 yr 11 mo ago | CONSTRUCTION OF ASPHALT OVERLAY ALONG ANAO-RAMOS RD - K0160 + 663 - K0162 + 419Roads | Completed | Tarlac DEO | ₱94.1M |
| 24CJ0369 | 1 yr 11 mo ago | CONSTRUCTION OF ASPHALT OVERLAY ALONG CAPAS-SAN JOSE-MAYANTOC MALACAMPA RD - K0158 + 140 - K0159 + 340Roads | Completed | Tarlac DEO | ₱94.1M |
| 24CJ0371 | 1 yr 11 mo ago | CONSTRUCTION OF ASPHALT OVERLAY ALONG PANIQUI-CAMILING-WAWA RD - K0161 + 252 - K0163 + 013Roads | Completed | Tarlac DEO | ₱94.1M |
| 24CJ0373 | 1 yr 11 mo ago | CONSTRUCTION OF ASPHALT OVERLAY ALONG ANAO-RAMOS RD - K0163 + 441 - K0165 + 430Roads | Completed | Tarlac DEO | ₱94.1M |
| 24CJ0377 | 1 yr 11 mo ago | CONSTRUCTION OF ASPHALT OVERLAY ALONG TARLAC-GUIMBA RD VIA VICTORIA - K0144 + 990 - K0146 + 757Roads | Completed | Tarlac DEO | ₱93.6M |