PhilGEPS awards
₱17.14B · 1,380 awards
DPWH contracts
₱13.80B · 620 contracts
Rank by recorded value
#69 of 23,487
More info
First record
Jul 28, 2009 (17 yrs 3 mo ago)
Latest record
Dec 8, 2025 (11 mos ago)
DPWH contractor code
31174
Where they work
Latest 25 from a total of 620 DPWH contracts
| Contract ID | Start | Description | Status | Office | Amount |
|---|---|---|---|---|---|
| 23PA0071 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY POBLACION TUI, DAGUIOMAN, ABRABuildings and Facilities | Completed | Abra DEO | ₱5.0M |
| 23PA0072 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY SALNEC, BUCAY, ABRAGAA 2023 CSSP | On-Going | Abra DEO | ₱5.0M |
| 23PA0077 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CALAO, BUCAY, ABRABuildings and Facilities | On-Going | Abra DEO | ₱4.7M |
| 23PA0079 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BA-I, LAGAYAN, ABRABuildings and Facilities | Completed | Abra DEO | ₱5.0M |
| 23PA0080 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BANGBANGAR, BANGUED, ABRABuildings and Facilities | Completed | Abra DEO | ₱5.0M |
| 23PA0082 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PACAC, DOLORES, ABRABuildings and Facilities | Completed | Abra DEO | ₱4.9M |
| 23PA0084 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PAWA, LAGANGILANG, ABRAGAA 2023 CSSP | Completed | Abra DEO | ₱4.9M |
| 23PA0085 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PANG-OT, LAGAYAN, ABRABuildings and Facilities | Completed | Abra DEO | ₱5.0M |
| 23PA0086 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY BAAC, LANGIDEN, ABRABuildings and Facilities | On-Going | Abra DEO | ₱4.7M |
| 23PA0087 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), LANGIDEN NATIONAL HIGH SCHOOL, LANGIDEN, ABRABuildings and Facilities | On-Going | Abra DEO | ₱4.7M |
| 23PA0088 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY DALAYAP, LANGIDEN, ABRABuildings and Facilities | On-Going | Abra DEO | ₱4.7M |
| 23PA0089 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY QUILLAT, LANGIDEN, ABRABuildings and Facilities | On-Going | Abra DEO | ₱4.7M |
| 23PA0090 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY PALAQUIO, BUCAY, ABRAGAA 2023 CSSP | On-Going | Abra DEO | ₱4.7M |
| 23PA0091 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY ABANG, BUCAY, ABRABuildings and Facilities | On-Going | Abra DEO | ₱4.7M |
| 23PA0092 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY QUIMLOONG, BUCAY, ABRAGAA 2023 CSSP | On-Going | Abra DEO | ₱5.0M |
| 23PA0107 | 3 yrs 7 mo ago | REHABILITATION OF BASAR-UD-UDIAO ROAD, SALLAPADAN, ABRARoads | Completed | Abra DEO | ₱96.5M |
| 23PA0111 | 3 yrs 7 mo ago | REHABILITATION OF POBLACION-LAGUIBEN-PANGILIB ROAD, LAGANGILANG, ABRARoads | On-Going | Abra DEO | ₱96.5M |
| 23PA0047 | 3 yrs 7 mo ago | SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURE PROTECTING PUBLIC INFRASTRUCTURE/ FACILITIES, CONSTRUCTION OF TOON-SAN GREGORIO FLOOD CONTROL STRUCTURE, LA PAZ, ABRAFlood Control and Drainage | Completed | Abra DEO | ₱144.7M |
| 23PA0105 | 3 yrs 7 mo ago | CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP), ALIMUSGAN-BAI-CAGANAYAN ROAD LEADING TO KAPARKAN FALLS, CAGANAYAN, TINEG, ABRARoads | Completed | Abra DEO | ₱12.2M |
| 23PA0110 | 3 yrs 7 mo ago | REHABILITATION OF CAYAPA-KILENG ROAD, LAGANGILANG-BAAY-LICUAN, ABRARoads | Completed | Abra DEO | ₱96.5M |
| 23PA0023 | 3 yrs 7 mo ago | OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVER, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER BASIN (PHASE II), CABOLOAN, BANGUEDFlood Control and Drainage | On-Going | Abra DEO | ₱92.5M |
| 23PA0054 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY UDANGAN, LA PAZ, ABRABuildings and Facilities | On-Going | Abra DEO | ₱4.7M |
| 23PA0056 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY BULBULALA, LA PAZ, ABRABuildings and Facilities | On-Going | Abra DEO | ₱4.7M |
| 23PA0058 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY POBLACION, PILAR, ABRABuildings and Facilities | Completed | Abra DEO | ₱5.0M |
| 23PA0073 | 3 yrs 7 mo ago | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CABAROAN, TAYUM, ABRABuildings and Facilities | Completed | Abra DEO | ₱5.0M |