DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction action

MUNICIPALITY OF STA. CRUZ, ILOCOS SUR Award a ₱989.5K contract to PRECIOUS CONSTRUCTIONMunicipalities

Transaction hash:
02845c219286bb5cf9146f8af68e50eca9c33ea6809c6694e6fc4bd4c4a43042
Status:
Included and unchanged
Block:
#1,354 4,659 blocks after it
Position in block:
Transaction 0 of 66
Award day:
Jan 18, 2012 (14 yrs 9 mo ago)
Value:
₱989,473.98
Project:
Supply and delivery of materials for the concreting of Sagat Road, Sagat, Sta. Cruz, Ilocos Sur

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #1,354 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    The award does not say which budget line pays for it.
    Not published
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    MUNICIPALITY OF STA. CRUZ, ILOCOS SUR awarded it to PRECIOUS CONSTRUCTION on 2012-01-18.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    No matching DPWH contract record (only DPWH contracts are listed with progress).
    Not published
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    No completion certificate published.
    Not published
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    COA's CY2024 audit of Santa Cruz gave a "unmodified" opinion on its financial statements (not specific to this contract).
    Partly

1 of 8 documents found, 1 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   02845c2192…a43042now      …
  2. 2. Block Merkle root changed
    stored   bd60abb482…aee506now      …
  3. 3. Block #1354 hash changed
    stored   5f0974bd5f…d83b19now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (7 steps)

How this one record is tied to the block's Merkle root, without needing the other 65 records. Each step hashes the current value together with the sibling shown.

  1. leaf  02845c219286bb5cf9146f8af68e50eca9c33ea6809c6694e6fc4bd4c4a43042
  2. 01 R 043070f695770cf2d7d4c7cb092f59a4f98535f091a3548217348047dfff09eb
  3. 02 R 748e61e8989d3033f399efba9095d55cb234b1eb9a1a4046e30e656697ede096
  4. 03 R 8cbeb24fd00298290a39470453fb47064ac2712c55fd1b17543090626ed2afa1
  5. 04 R 828144ea0fc49022cab8be83ae1244c76c7035fddd1c9ecb4d4c01d9cf81be85
  6. 05 R 30b333765c5d8edc4bdfa41e656b7d36af827dfaf663ef7af027f13f06722f4d
  7. 06 R 9289be85191966215c0e093b38c95f0880ff9961a181cc3333ed2784909d99d2
  8. 07 R 514ff28e345d2c1582f18d00ff16603ed71ae095c5dd85a4957541140a586427
  9. root  bd60abb48227099f8974951389f831597b63c66c422a5d2befbcc6194baee506