DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SURIGAO DEL NORTE Award a ₱2.9M contract to AMA CONSTRUCTIONNational agencies
Transaction hash:
0678772dfa4d0d8e809de816ff2667c526d5f0a89b60d47e1451679db27edd00
Status:
Included and unchanged
Block:
#4,221 1,792 blocks after it
Position in block:
Transaction 2 of 244
Award day:
Sep 14, 2020 (6 yrs 2 mo ago)
Value:
₱2,910,819.90
Project:
20NG0092
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,221 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2020 LP", i.e. the FY2020 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SURIGAO DEL NORTE awarded it to AMA CONSTRUCTION on 2020-09-14.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 20NG0092: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2021-03-31). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 0678772dfa…7edd00now …
- 2. Block Merkle root changedstored 1e07e577d1…089a05now …
- 3. Block #4221 hash changedstored 79f88cd2a1…634de4now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (8 steps)
How this one record is tied to the block's Merkle root, without needing the other 243 records. Each step hashes the current value together with the sibling shown.
- leaf 0678772dfa4d0d8e809de816ff2667c526d5f0a89b60d47e1451679db27edd00
- 01 R 07585bbeeac421da5b315c390bad1c65adc34b598028ed5877edee0032673061
- 02 L 022c27e9515517bbdc05654ddbcd6916d2406415d089fd49a4098d299a9de7c7
- 03 R f0d0ea4967b838f71e204f8d3a1c7f3442de384e0632e7d16e0f771cf498461c
- 04 R 3270b2569bbe1406876ef049ae1cbbb8d96929b68d234b3181129fafdd7c74ba
- 05 R 14e93ba3345962bfd756a42b768a183ae2235021d3a9a18f6e5fe0f75536a9c1
- 06 R 5835b2ac10b42950ed739405dfc74dc4781b49fd15b53d99c8a8a8dae7922e44
- 07 R b8c9b671b6eac1efa8f3241c0ce317372b08817b5bb67e5d3379608f5a1b9d7a
- 08 R 44c76c6b44325253a6945ef251f8635be0ab25a8a5b660c397c4be4c86e4deb2
- root 1e07e577d1e4edfe882395a36d191c546850ca32f098692b0aadadf1cf089a05