DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 3RD DEO Award a ₱2.0M contract to AFG ZILLION CONSTRUCTION CORPORATIONNational agencies
Transaction hash:
0c26a84db5bc1bf6b26fad7289f1f0d538f4045bec05fdbf5259f2aeb5e210b3
Status:
Included and unchanged
Block:
#3,399 2,614 blocks after it
Position in block:
Transaction 14 of 274
Award day:
Apr 24, 2018 (8 yrs 6 mo ago)
Value:
₱1,974,684.44
Project:
18GH0115
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,399 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2018 LP", i.e. the FY2018 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 3RD DEO awarded it to AFG ZILLION CONSTRUCTION CORPORATION on 2018-04-24.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 18GH0115: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2018-07-22). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 0c26a84db5…e210b3now …
- 2. Block Merkle root changedstored b48142407f…590710now …
- 3. Block #3399 hash changedstored 120a6b4df6…45a80dnow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (9 steps)
How this one record is tied to the block's Merkle root, without needing the other 273 records. Each step hashes the current value together with the sibling shown.
- leaf 0c26a84db5bc1bf6b26fad7289f1f0d538f4045bec05fdbf5259f2aeb5e210b3
- 01 R 10591d79373ef027b92e0ce3983a710941fc9cac7b099b2fe0334ba4ff92f6de
- 02 L 78a473ee88151b69b79b6456404331c1c78353886ea71ee23cfa20d213f9504e
- 03 L eccf39999b3e3a4c218a7a80a216c4036d2641ef3949409e382e86f7b529d99e
- 04 L 4779789a530f04eb30b69d5c213eb8b74477735a6c690f32e0bc353316b43eb7
- 05 R b09d960a1c2d670f6e56f1bced0cde6bff0c9eb003eae1ff178e2a22a284b799
- 06 R cef048e475893735c5696ef0b3a25b9ae6712b496265167939df37e5dca24374
- 07 R aae302f2aac829e21bfe3e60fc1bf9fcbb8923b8556a40f2a5f993455abc691c
- 08 R 07d77dfacbda8e06bdd28d79ee0a4fff337a3419e9510883d09e99ff2ad77d97
- 09 R 82516f25e7f8cd8965e89fad1a49366ff8a51b99bad453c106d324a397959a8d
- root b48142407ff2e68a365486563275cc8be2275dbbb131f746c3d3de69df590710