DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO Award a ₱1.5M contract to TRIPLE PEAK MOUNTAIN CONSTRUCTION AND SUPPLYNational agencies
Transaction hash:
0e52f7377a9ce22d56453ee365bca4498275d3b47b7a53c88fef166c5ff196f2
Status:
Included and unchanged
Block:
#4,134 1,879 blocks after it
Position in block:
Transaction 9 of 121
Award day:
Jun 16, 2020 (6 yrs 5 mo ago)
Value:
₱1,537,260.84
Project:
Rehabilitation/Reconstruction of Road
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,134 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2020 OO-1", i.e. the FY2020 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO awarded it to TRIPLE PEAK MOUNTAIN CONSTRUCTION AND SUPPLY on 2020-06-16.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 20EH0044: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2020-08-18). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 0e52f7377a…f196f2now …
- 2. Block Merkle root changedstored aaf947ae5f…e28cc8now …
- 3. Block #4134 hash changedstored 90bbf81a85…352b0dnow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (7 steps)
How this one record is tied to the block's Merkle root, without needing the other 120 records. Each step hashes the current value together with the sibling shown.
- leaf 0e52f7377a9ce22d56453ee365bca4498275d3b47b7a53c88fef166c5ff196f2
- 01 L 0d0b8a9f2d302ee5791b3add3d541357e0c13fbd9fdd787d5dbf09fe687476d7
- 02 R ddc4d83d8ec2dbe758832d65d4445cd1be8102026db40848d4b26b7913c30bc7
- 03 R 32cc3e8e0638bb7c27ff6590f3777b2f4e05757a02829bc7e0e30878dbae197c
- 04 L 8fa0874fff42a72f3859d47ea8e168d79721b8cbd5c839b0803051d97dbd5bae
- 05 R 2add5e2f8994f6273fa97eb9e92777d478efad6912735fdd59b9c5beb5bf766a
- 06 R 06d5af8a59ac5be17d0a9189f3959e22b2ff45bd08388be2f0721cdd74c6a7f0
- 07 R cfacd9cea0c052fff9b7c64a1042dba45b99f451a0e2c7e5d9cb7618c90d8d47
- root aaf947ae5ff3def0b6dec4317032dbc0a2c4e3450f104c16da24b86e97e28cc8