DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
MUNICIPALITY OF SOCORRO, ORIENTAL MINDORO Award a ₱3.0M contract to ANSAVILLA CONSTRUCTION AND DEVELOPMENT CORPORATONMunicipalities
Transaction hash:
197d578ff63c996b80d6dc563d5d1af7765a9966f3051664cad752c73cba3192
Status:
Included and unchanged
Block:
#3,763 2,250 blocks after it
Position in block:
Transaction 91 of 831
Award day:
May 15, 2019 (7 yrs 6 mo ago)
Value:
₱2,995,403.96
Project:
Establishment of Water System Level II at Barangay
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,763 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)The award does not say which budget line pays for it.Not published
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)MUNICIPALITY OF SOCORRO, ORIENTAL MINDORO awarded it to ANSAVILLA CONSTRUCTION AND DEVELOPMENT CORPORATON on 2019-05-15.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)No matching DPWH contract record (only DPWH contracts are listed with progress).Not published
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)No completion certificate published.Not published
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)COA's CY2024 audit of Socorro gave a "not stated" opinion on its financial statements (not specific to this contract).Partly
1 of 8 documents found, 1 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 197d578ff6…ba3192now …
- 2. Block Merkle root changedstored 1966c664c3…66a6ffnow …
- 3. Block #3763 hash changedstored 7af5ae1677…b4e95anow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (10 steps)
How this one record is tied to the block's Merkle root, without needing the other 830 records. Each step hashes the current value together with the sibling shown.
- leaf 197d578ff63c996b80d6dc563d5d1af7765a9966f3051664cad752c73cba3192
- 01 L 19769b24ca502e35ff3468f77406974c41c6ef1a7526b8041555bf5adf90de00
- 02 L dab7f4243e03373fbd4e356246d8908e80ba44879d81559a584bf747da6fa5c9
- 03 R dd42c6ad964fa267a6350a0564dd301bc608783886445c99928128ab85bb6f45
- 04 L edd3278de2b50f3444cdff918693d71c24f2697b3efcca233e7aeeb374c1c567
- 05 L 4e8a4fc26e8f1d66ca761045c719e9b258917a232cae0b558a5b3fe3c2b1c9ac
- 06 R 0f28e9655d36b943b49b2aebdc300091c4dd9e75123790d1a3303a7f474307df
- 07 L cc79477b513ee7d3d600f6f1617ce6db8587a1f4856c9dba5c7ffb6433e69f32
- 08 R 55a19b4d40baf442b4af54e27da8f275fe613bcf9bfb1192b0dd4dc5ab459f8e
- 09 R 2cd2d6613b387c539762e996b13c85e7f7f0ba0b18f5c11b761c5108541a58f0
- 10 R 19adb7ceaccc15269eac72a0084a4afac5290f5705641dbe1863b771dd8c2a1a
- root 1966c664c37e4445673ff88fe5f27d06f85262c371055d9cb6e93da0bc66a6ff