Skip to content
FY2026 GAA: ₱6.79T
PisoScan
DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction hash:
1d02b06c98d8b4807162c91acbb407003e963e1c58882cb21d0103801993c0ac
Status:
Included and unchanged
Block:
#3,772 2,241 blocks after it
Position in block:
Transaction 77 of 706
Award day:
May 24, 2019 (7 yrs 5 mo ago)
Value:
₱6,957,193.73
Project:
19EI0051 - Const of Mirayan Bailey Br at Sitio Cen

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,772 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Regular Infra - GAA 2019 LP", i.e. the FY2019 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTHERN MINDORO E awarded it to MONOLITHIC CONSTRUCTION AND CONCRETE PRODUCTS, INC. on 2019-05-24.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 19EI0051: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2020-03-26). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   1d02b06c98…93c0acnow      …
  2. 2. Block Merkle root changed
    stored   bf683cb1d1…336434now      …
  3. 3. Block #3772 hash changed
    stored   f3a87bd759…e2c77enow      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (10 steps)

How this one record is tied to the block's Merkle root, without needing the other 705 records. Each step hashes the current value together with the sibling shown.

  1. leaf  1d02b06c98d8b4807162c91acbb407003e963e1c58882cb21d0103801993c0ac
  2. 01 L 1ccfb847aac4dbea67fd87d0da74e26cfb6ae2f6833348678fa9bfec0edb41aa
  3. 02 R c0001c295d775a205b6264770f45feab07eb75390cc2dd9979715e52fac9e0e1
  4. 03 L f7d63a724b44df95b6bcf42e797a770da7b76ce0e053f41c420cf9723c492979
  5. 04 L 9d916b672b2930256d4404f8d2f189c4f26f8f0051d773b6f68c7a2a4794ed40
  6. 05 R e4eed1ba37bb7de78ff51283dfec120f876eb97827ce00948f1cc7ccd5d0610c
  7. 06 R 9350b159572e6b9d67dd19c93388e4e411ba05e402c28127fa868e58cce9ea11
  8. 07 L e90d6b712eb9211b67c73bcfcbd0d4db4bbd41bf902ecb379f71ca673cf27572
  9. 08 R bd20d8c819b05e6bbf15bb64b2dceb44d9ee8f3e37f6f2307fa266d546df0783
  10. 09 R 80c085af5641b4f59af99ce3561e937212d487f9f67ded440d9453cc593ba668
  11. 10 R ba79f91789622e4c9c6616f8cedc13befb6f87ea2d87b0521dfda3f90b8a2907
  12. root  bf683cb1d1468c1f27c5828452e975a63050364e01f0fde5f12acc0110336434