DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CEBU 6TH DEO Award a ₱19.9M contract to P.B. OBIAL CONSTRUCTIONNational agencies
Transaction hash:
2a661180a659bec797d6abdcbdf06eec0c1e2471471df8261f7ffae8dedfacf6
Status:
Included and unchanged
Block:
#2,844 3,169 blocks after it
Position in block:
Transaction 23 of 163
Award day:
Sep 7, 2016 (10 yrs 2 mo ago)
Value:
₱19,910,000.00
Project:
16HN0065
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #2,844 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Outside Infra - GAA 2016 DepED BEFF", i.e. the FY2016 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CEBU 6TH DEO awarded it to P.B. OBIAL CONSTRUCTION on 2016-09-07.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 16HN0065: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2019-10-07). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 2a661180a6…dfacf6now …
- 2. Block Merkle root changedstored 2fd190fe45…82ed77now …
- 3. Block #2844 hash changedstored 67a9b2bc49…0f9dbenow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (8 steps)
How this one record is tied to the block's Merkle root, without needing the other 162 records. Each step hashes the current value together with the sibling shown.
- leaf 2a661180a659bec797d6abdcbdf06eec0c1e2471471df8261f7ffae8dedfacf6
- 01 L 23f2beded8c588560c006619f2523b77a2f03367c581abb775ac7a312001163a
- 02 L 3297306f60b253961dca450a9e6213fa8bee840936df1c01bbe997d02c4bad7f
- 03 L 2c5d3bf21466c989fe1cf1ce0f3031387405cf5199dd11307eb49ccf75738384
- 04 R 2845fa5888c26bc58a3f737ef12bbc7640425ab83bf6c9f8ec0456eceb112a0c
- 05 L 03252c5015dd02bb408f42a85921236f50be8ed722717eef926b4324cc34b09a
- 06 R 36f27a4b134e990a46d224e93c791048333fec69d12e7265ea2a172f7ac94b60
- 07 R 7d3db9f1e2dc1ee7d255f96b70c1c87726226c22e35356b24b0c579df2b51c75
- 08 R 37c4161fc893ac34e526efd60a1afe005a6f7dfcbb847537d7323624772abc30
- root 2fd190fe452fb31fe31f90af61aebce545415ec6f805675b75ba4eff3182ed77