DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction action

MUNICIPALITY OF SANTA MARIA, ILOCOS SUR Award a ₱2.5M contract to JENBA CONSTRUCTIONMunicipalities

Transaction hash:
2cd50dd7e01b37569952b1163f5678e31ff6a3edc128fec8e6b5df382aa68c0f
Status:
Included and unchanged
Block:
#3,339 2,674 blocks after it
Position in block:
Transaction 51 of 302
Award day:
Feb 20, 2018 (8 yrs 8 mo ago)
Value:
₱2,498,818.53
Project:
Construction of National Child Development Center

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,339 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    The award does not say which budget line pays for it.
    Not published
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    MUNICIPALITY OF SANTA MARIA, ILOCOS SUR awarded it to JENBA CONSTRUCTION on 2018-02-20.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    No matching DPWH contract record (only DPWH contracts are listed with progress).
    Not published
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    No completion certificate published.
    Not published
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    COA's CY2024 audit of Santa Maria gave a "qualified" opinion on its financial statements (not specific to this contract).
    Partly

1 of 8 documents found, 1 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   2cd50dd7e0…a68c0fnow      …
  2. 2. Block Merkle root changed
    stored   216e8c3433…5d5f7bnow      …
  3. 3. Block #3339 hash changed
    stored   070c3e4712…f6b8e8now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (9 steps)

How this one record is tied to the block's Merkle root, without needing the other 301 records. Each step hashes the current value together with the sibling shown.

  1. leaf  2cd50dd7e01b37569952b1163f5678e31ff6a3edc128fec8e6b5df382aa68c0f
  2. 01 L 2b920c0b896c6b254365e8216a2320c45b548215db0de28e898e9dba40cde7b9
  3. 02 L 4dfe34132aec7400c4d7624265bd457e933844eb2a33464f12a751bac089f23d
  4. 03 R b1a5b5895a3cdb40ae2110c0931833dd907968e8219c98785d2d6cad0946673d
  5. 04 R cd8ad3b2652a83e090f373536e636ee9cb15851a33be157b3f5e70d8ef4d15e1
  6. 05 L 9be60b004bec7dae0581754fd63339dbeacf4a0fdaedec23690b1b6529483f5d
  7. 06 L b0d8636140b358c56370123dc632ce2050decd83099d6f3b3606da0c864d7770
  8. 07 R f5f7af228d9f51b22f8e03a6ab7ea7fe14de75f58fdd330edb9c0e94305e48e4
  9. 08 R 73d33bd4f493901c1fbb66770f89dbc5179c1bb840a0bd4766e390cc3217740e
  10. 09 R b19fc29c1d7f56a510373adb2896035a80141bf3e91961acf0d5721ad98867d0
  11. root  216e8c34331259e58952b65a1c7fe16b45a7ebd1012f9d2adaf9b88d835d5f7b