DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 5TH Award a ₱39.4M contract to SISAM CONSTRUCTION AND SUPPLIESNational agencies
Transaction hash:
319a08b2eaa59414285682c1fc00d2067753a9862db2c472d6f5d3624af5de75
Status:
Included and unchanged
Block:
#4,426 1,587 blocks after it
Position in block:
Transaction 54 of 300
Award day:
Apr 20, 2021 (5 yrs 6 mo ago)
Value:
₱39,418,236.20
Project:
21FN0089
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,426 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2021 OO-2", i.e. the FY2021 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 5TH awarded it to SISAM CONSTRUCTION AND SUPPLIES on 2021-04-20.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 21FN0089: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2021-09-20). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 319a08b2ea…f5de75now …
- 2. Block Merkle root changedstored 03e92cd5b0…569440now …
- 3. Block #4426 hash changedstored 15736abae9…a81ff8now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (9 steps)
How this one record is tied to the block's Merkle root, without needing the other 299 records. Each step hashes the current value together with the sibling shown.
- leaf 319a08b2eaa59414285682c1fc00d2067753a9862db2c472d6f5d3624af5de75
- 01 R 329619bdc6b75f60322f78a7efb358e90b56d5e89f18532ebdc04a5b6c1ea047
- 02 L 1cb5fffec0e9c6323ca57482eff69022c0236e835673208012d68d8e4ca4a873
- 03 L 0dfbdad5e980bd014794cf3e3f570d62ed9f97571697fd6cbaa05828c26b7735
- 04 R f9cb8c79ee22db07f68f7506d7576ae6623654077e50b3e45e0885a7d95da6ee
- 05 L 134f7ac84db7704220d39ffcf7f3f27fa21648eac10385bb1c3927a80194ebfc
- 06 L 73a03679c6fbc9789fda40e21dcff552c764d234925442ebf59b7ec1b573a12d
- 07 R ea89de2f34d73361c99843a69856097fb1076c9996d793fbf15ff40027744339
- 08 R 23075588774da60187b5f10b60a18bd475ccf26690917391323c20387b77a972
- 09 R d5d45c7fbf277b5ae085f63b2047a617d6d858d0d02316c50f30ac82dab0b5e5
- root 03e92cd5b0bdb1b8da1273edf4114421489a04b8bb7cb1c24c2377eab5569440