Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 1ST DE Award a ₱2.8M contract to F.C. MARTINEZ CONSTRUCTION DEVELOPMENT AND SUPPLY CORPORATIONNational agencies
Transaction hash:
37d64d1330a3fcdcf238ff9a167a3daa00ca14ca5f5339b12b5022c812eb1f60
Status:
Included and unchanged
Block:
#5,757 256 blocks after it
Position in block:
Transaction 165 of 729
Award day:
Jan 30, 2025 (1 yr 9 mo ago)
Value:
₱2,758,075.21
Project:
25CE0141
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #5,757 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2025 SSP", i.e. the FY2025 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 1ST DE awarded it to F.C. MARTINEZ CONSTRUCTION DEVELOPMENT AND SUPPLY CORPORATION on 2025-01-30.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 25CE0141: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2025-04-30). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 37d64d1330…eb1f60now …
- 2. Block Merkle root changedstored 1cbc48d226…54d638now …
- 3. Block #5757 hash changedstored 78828435d1…6377e9now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (10 steps)
How this one record is tied to the block's Merkle root, without needing the other 728 records. Each step hashes the current value together with the sibling shown.
- leaf 37d64d1330a3fcdcf238ff9a167a3daa00ca14ca5f5339b12b5022c812eb1f60
- 01 L 373fae6b8485c57cbe6beebd3691b8234aac3bf26a06c1bf8ce3c053ecf3a39b
- 02 R 20b114770980c81b403a291251a2b65bb0e91fcfa7993e58c1f04bf24d1ed6fa
- 03 L 8154232f0a6d17fd29a14525d925f0a19488bafd52094ae338b7ccff0853817b
- 04 R 7ccb104f7fc4cc4bc75fc389e3b277bf83e95b0c9e6619384cce42ebf7b20296
- 05 R 89f00ee8500e97d9bac59d5d714aaf9a93c7333a1cb0b94c99c979e71f41d133
- 06 L 0471995b2365d6bbf7076403642986e5c286d1641b8d0e6560e76c39306288ce
- 07 R 610cb8074d2aa1921ff450fa514aafe0479a1520db91829b0c63e6e0c3ea817d
- 08 L 041b3bdbbd5563cb2158bd5688b1c574bdc026c625cfb4e04823a3d5b719a78c
- 09 R 50dd1c7cc37ef4270b31baa92b01b3fa8687906f44555c8a86bcb9a20dc4ac25
- 10 R 441c9841024a046d4be80a6236790fc9b086465f6591fd4e4ff8769c40c767bf
- root 1cbc48d226b1764f87c47031ba3a5ecee58ec2f9cfc232e3cc80d3996f54d638