DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAVITE - SUB-DEO Award a ₱877.0K contract to M.S. RAMOS CONSTRUCTION INC.National agencies
Transaction hash:
39da7cb2f2f88854b7e4168d3cdc1f9adaf9e56e49e584ccc4ee06138d42113f
Status:
Included and unchanged
Block:
#1,292 4,721 blocks after it
Position in block:
Transaction 26 of 103
Award day:
Nov 11, 2011 (15 yrs ago)
Value:
₱877,014.43
Project:
Construction and Rehabilitation of Multi-purpose Building at Brgy. Bancod, Indang, Cavite and School Building at BLISS E/S, Biga II, Silang, Cavite
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #1,292 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)The award does not say which budget line pays for it.Not published
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAVITE - SUB-DEO awarded it to M.S. RAMOS CONSTRUCTION INC. on 2011-11-11.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)No matching DPWH contract record (only DPWH contracts are listed with progress).Not published
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)No completion certificate published.Not published
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
1 of 8 documents found, 0 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 39da7cb2f2…42113fnow …
- 2. Block Merkle root changedstored 181eaf46d6…394f74now …
- 3. Block #1292 hash changedstored 1dd3723d51…67234bnow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (7 steps)
How this one record is tied to the block's Merkle root, without needing the other 102 records. Each step hashes the current value together with the sibling shown.
- leaf 39da7cb2f2f88854b7e4168d3cdc1f9adaf9e56e49e584ccc4ee06138d42113f
- 01 R 3c0ed66c60603737d4245a39be513d892234ba35f3c410e8ba2ed53fe0c7f35c
- 02 L e86738a378eb5a5903711130baccf34eebbf9b88dec7174d6659b0c53b622128
- 03 R 5b708d4acce718362dce245a28fab167feb3ba950ba4e07d804547bbda9914d9
- 04 L db7c4fbbb301d92bd734b83a01c23189fa93a397d81267edbf7026a955cd79d1
- 05 L 54b8a7c609ccdf16417a4b29a146461c6b955075208344370ddafc2465c0376a
- 06 R ddaf37c8e88fbc4bb074110ff8fc4335994fd5f494d6130ff0ee89f0a3d2a7f3
- 07 R b2b3a48557bd049c5502bcd5c1f167c426b08a695bb2e734a5ed7d483dad1eda
- root 181eaf46d6ae5ed30625026ff98470b784c55a893b50c8b7470628a77e394f74