DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTHERN SAMAR 2ND Award a ₱3.1M contract to CDU CONSTRUCTIONNational agencies

Transaction hash:
4312f5efcdf2c505af70cf7075f4393c4d57092d94060f3e6a91b83a5c4dfa69
Status:
Included and unchanged
Block:
#4,973 1,040 blocks after it
Position in block:
Transaction 75 of 267
Award day:
Nov 11, 2022 (4 yrs ago)
Value:
₱3,148,600.00
Project:
22II0077, Construction/Rehab. of Water Supply

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,973 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Regular Infra - GAA 2022 CSSP", i.e. the FY2022 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTHERN SAMAR 2ND awarded it to CDU CONSTRUCTION on 2022-11-11.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 22II0077: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2023-02-23). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   4312f5efcd…4dfa69now      …
  2. 2. Block Merkle root changed
    stored   d74104ff0e…96003cnow      …
  3. 3. Block #4973 hash changed
    stored   9d3538ef16…141091now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (9 steps)

How this one record is tied to the block's Merkle root, without needing the other 266 records. Each step hashes the current value together with the sibling shown.

  1. leaf  4312f5efcdf2c505af70cf7075f4393c4d57092d94060f3e6a91b83a5c4dfa69
  2. 01 L 42faf417f81b0841cc0c628387f4d9ab69b1e69599fc5224d0827e4fe80e22cc
  3. 02 L bc465cd7e91b30bc5496e8979c822e85ad850710edf591f3aaa17a7913addbf4
  4. 03 R e0497e8a7fb1c98f983d519ac459bc86609072ebd69e97152fc7fbcae23e9c03
  5. 04 L 79b7af1dc34c5fa371bb3db888b1915e0d65510cfe45fd51e2123b313684f35e
  6. 05 R 46efa4678baea37d3edaef07e3e1e509ea52d213645fc91bca0cee35b4766c4e
  7. 06 R 45a524beecea6f52dac8378cfb51feef10f7a77714900fbd0f496618f4473c70
  8. 07 L c8a6d689ac0969f125facc514ecc1d0fb60394b6307f6b5c6ebcc23e9cc70e5c
  9. 08 R e3c673805a0275c6cc071519decba0075f72e0949baf754b45ba9fac60468188
  10. 09 R dd10e9a9917fe9c624f447beb93db25b8cf653f7b27e98c173b19e2b7be01a61
  11. root  d74104ff0e839acc5bd13ac9d4f4b545612e3b9feeed9e8293e5056e2996003c