DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES NORTE ED Award a ₱21.2M contract to SHEAR CONSTRUCTION AND SUPPLYNational agencies
Transaction hash:
48fe778c7080460babfa4b6bf466b21972180941da58340b44cf1d72b2bd03a9
Status:
Included and unchanged
Block:
#3,286 2,727 blocks after it
Position in block:
Transaction 18 of 51
Award day:
Dec 26, 2017 (8 yrs 10 mo ago)
Value:
₱21,195,865.45
Project:
17FC0344
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,286 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Outside Infra - GAA 2017 DepEd BEFF", i.e. the FY2017 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES NORTE ED awarded it to SHEAR CONSTRUCTION AND SUPPLY on 2017-12-26.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 17FC0344: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2018-10-27). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 48fe778c70…bd03a9now …
- 2. Block Merkle root changedstored 63d15330aa…28cf43now …
- 3. Block #3286 hash changedstored 8499058c3a…a11725now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (6 steps)
How this one record is tied to the block's Merkle root, without needing the other 50 records. Each step hashes the current value together with the sibling shown.
- leaf 48fe778c7080460babfa4b6bf466b21972180941da58340b44cf1d72b2bd03a9
- 01 R 4f71f09e79a4dd08547c46c26cca3394474e283f069afce605456a47981f3a96
- 02 L 2a029617851f3891e67f4d7b7db1b41edad2983c3c27eb1b012909cc18e647b0
- 03 R 262061b13577583f58ad186728003eed9fa75334da9ae291d772852b84a5ab91
- 04 R 5f215944b4609dd64d8bccbfd19b6e517745d51550a13fd0832b30f0cb7ccf47
- 05 L 5fd3c8f57dc7a9386e7c88e530a389cd3a00ed57bf689069862f2e1198ede951
- 06 R 809e82028bb83b3f894762221da00e9284f01f9bdf2e54a22b82f5b40a2e3f77
- root 63d15330aacbe50a725c78fe7be692b91238bf800b19169a012482947c28cf43