DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO 1S Award a ₱11.9M contract to A.L. ACHARON CONSTRUCTION AND SUPPLYNational agencies
Transaction hash:
4d4d8b5a1e3265cbe91d287ef1eb589a52aae78fc85b9f2015bec31bce38dc7d
Status:
Included and unchanged
Block:
#4,933 1,080 blocks after it
Position in block:
Transaction 83 of 258
Award day:
Sep 30, 2022 (4 yrs 1 mo ago)
Value:
₱11,863,846.81
Project:
22MB0128 - Concreting of Purok 7 to Purok 20, Brgy
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,933 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Outside Infra - GAA 2022 DA FMR", i.e. the FY2022 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO 1S awarded it to A.L. ACHARON CONSTRUCTION AND SUPPLY on 2022-09-30.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 22MB0128: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2023-02-16). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 4d4d8b5a1e…38dc7dnow …
- 2. Block Merkle root changedstored 2e51722a68…3ec046now …
- 3. Block #4933 hash changedstored 3da0629f8a…896411now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (9 steps)
How this one record is tied to the block's Merkle root, without needing the other 257 records. Each step hashes the current value together with the sibling shown.
- leaf 4d4d8b5a1e3265cbe91d287ef1eb589a52aae78fc85b9f2015bec31bce38dc7d
- 01 L 4cff272e0f145eb0da37be33ec921af62d668bc111a05e95fee6b323eddedbe0
- 02 L 0ada865f3171256f8f4ff5e1a8c7ddd41c2e6f783bcbdbad763aec62efc95ed1
- 03 R 23111490c604abde90aaa87de1bae4bfe75150e6e6e32dac10e09b72253c7a21
- 04 R 14f41c8d41323cc505e40c033df0f78a3badf3ddcc708e7d871072567d53c7a5
- 05 L 496ba5a0f0ed081f6676763642c8718d14b8a429d5d29ce271b0dcb87eed30d8
- 06 R ef4f1d3bdee4be3d9740214d40dcea14ab05bdacf414a1f126a387ac9965a2b3
- 07 L 5951d1794463caa114025353ace26fecb2b78bc9161e2d069f90ec439fe1bf3d
- 08 R 58bf78719f43606e1d7e5c1f95198d860c469a20172902d1a69d6679bfccc627
- 09 R a0f631dc9513b3d1fa7d8b4660252dbaa2a49ac9bfee2455bc8ed3b189e68311
- root 2e51722a68377373a2e8c9801847cb41e66322f56f4ea7ad4b775ea9bd3ec046