Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAVITE II DISTRICT Award a ₱4.8M contract to 888RV CONSTRUCTION AND SUPPLIESNational agencies
Transaction hash:
560e6679970b1054dbeefe896101810ceb23d99ab7cb9f717d90d3a50c010a6e
Status:
Included and unchanged
Block:
#5,169 844 blocks after it
Position in block:
Transaction 163 of 408
Award day:
May 30, 2023 (3 yrs 5 mo ago)
Value:
₱4,795,935.95
Project:
23DG0028
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #5,169 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2023 CSSP", i.e. the FY2023 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAVITE II DISTRICT awarded it to 888RV CONSTRUCTION AND SUPPLIES on 2023-05-30.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 23DG0028: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2024-05-09). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 560e667997…010a6enow …
- 2. Block Merkle root changedstored c4c44d239b…dd534anow …
- 3. Block #5169 hash changedstored 672c9e47e8…773cf5now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (9 steps)
How this one record is tied to the block's Merkle root, without needing the other 407 records. Each step hashes the current value together with the sibling shown.
- leaf 560e6679970b1054dbeefe896101810ceb23d99ab7cb9f717d90d3a50c010a6e
- 01 L 559e42d7d329be82be336afa65c1b835f22c50e3404c96cfff481ec028dd55b0
- 02 L 2fa8164f7166869aea2526c2fa3190e17cda332b487070311d2e247c92dcd3c1
- 03 R 6232b1da9955e0aa0cf3d6b9d55b468a2c9f3245fb389e2d39a9897297be3182
- 04 R 4024f93c8ea12d6752e840aab62800e72538a923ce37cf07d6a38ac40ed61490
- 05 R 9acb2a5d5cc39c71ab6d5a836f988b83ce2a30f59b1ba07ae1203389a2d998ff
- 06 L f1a01e8589ae6f54ab6b255aa938649804c90fef688c8fb947c2d5d6943cb2df
- 07 R efcd937ed21791ae8fd7dd67f32558c6671cd123f07c616d3a323b115a79729c
- 08 L b6ddc15f25d9af3d3336b2e1fe79801f7b3e27ed8ebaa775e4c29d5f62682fde
- 09 R f6a35e715514c83c7bbc075409c315e498f15bf994d7654f6714f81565c56209
- root c4c44d239b55e9a7d420486625996af59d53456b3c4bbfe5735d07d4ebdd534a