DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - N. VIZCAYA 2ND DEO Award a ₱1.9M contract to PISCES CONSTRUCTIONNational agencies
Transaction hash:
5cf246f3dc400ea0b0ade393ebdba14b53cbb11a64f61381382d976a621ba55f
Status:
Included and unchanged
Block:
#2,626 3,387 blocks after it
Position in block:
Transaction 101 of 293
Award day:
Jan 4, 2016 (10 yrs 10 mo ago)
Value:
₱1,912,224.14
Project:
Construction, Tactac Multi Purpose Bldg.
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #2,626 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2016 Locally Funded Projects", i.e. the FY2016 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - N. VIZCAYA 2ND DEO awarded it to PISCES CONSTRUCTION on 2016-01-04.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 16BJ0004: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2016-04-15). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 5cf246f3dc…1ba55fnow …
- 2. Block Merkle root changedstored 38163ff808…687281now …
- 3. Block #2626 hash changedstored 9e5fde3cc6…2c8fa4now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (9 steps)
How this one record is tied to the block's Merkle root, without needing the other 292 records. Each step hashes the current value together with the sibling shown.
- leaf 5cf246f3dc400ea0b0ade393ebdba14b53cbb11a64f61381382d976a621ba55f
- 01 L 5c90318a27fce614837541dcbda4af5db8ebe0145445afaba93745136aa077f8
- 02 R c7a7306074a70b4d29aea81b26b762866a9841dd21c4255efb1c2262f4a0a845
- 03 L 4acd27e779cba0a7693a5dc5fcfcf0aca195c6753d5926fc87178db84749f345
- 04 R 1b5532cbec95cfea4475f91073cc4167f98cca28be212f992323b72cee0f4d50
- 05 R 2e018cb738fd5e38fc66e6af360e52b683852845355249c72d862ba59ff81214
- 06 L e759d1e0f91a99812d18e63f1f22658d681efa929dbdf4f4b6042d115cd04b5a
- 07 L 86b89f3dbd613877cd9ccef7634758bb285aec35e1a0a03ff3f25b550433abb4
- 08 R 4f38fa5cc3a4a4ac78990b1260f38da5f6079da98fba14be43fb1f1836bf654a
- 09 R 1d1c9a41c62fbf6bacf0228f6973ba24dad9456ae185afacdf0a6554f0ef93c9
- root 38163ff80810034a657e102acbb44d72713a2d790b8e3a0e650dacfbd3687281