Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MISAMIS OCCIDENTAL Award a ₱42.7M contract to MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATIONNational agencies
Transaction hash:
70e9c91cd94442198ccb7a5d23c837f3046eb92a20c9142f7add270e2ddfbdc4
Status:
Included and unchanged
Block:
#3,635 2,378 blocks after it
Position in block:
Transaction 4 of 12
Award day:
Dec 29, 2018 (7 yrs 10 mo ago)
Value:
₱42,715,838.68
Project:
18KI0116 - Construction of 4-Storey 16 CL School B
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,635 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Outside Infra - GAA 2018 DepEd BEFF", i.e. the FY2018 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MISAMIS OCCIDENTAL awarded it to MONTAÑO CONSTRUCTION & DEVELOPMENT CORPORATION on 2018-12-29.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 18KI0116: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2019-11-25). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 70e9c91cd9…dfbdc4now …
- 2. Block Merkle root changedstored ef41c1345a…e0bc5dnow …
- 3. Block #3635 hash changedstored 47b0348187…f19becnow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (4 steps)
How this one record is tied to the block's Merkle root, without needing the other 11 records. Each step hashes the current value together with the sibling shown.
- leaf 70e9c91cd94442198ccb7a5d23c837f3046eb92a20c9142f7add270e2ddfbdc4
- 01 R 808513a03627d76a004eb7e70d6331499e91248fc865f3ce5933ec834cb475bf
- 02 R df641d9e7a7c69565aab282f54ee3e7807c730450da17f5c1a51787be1bcbc59
- 03 L c947f4279cb8394b3448870bd0a83cbe7cfe30adf9225638c447f7e2bbae9edc
- 04 R 03f72d9b58064dcd442fc6d0b5541225f6078b32667d9aef74f58ba32e09ab28
- root ef41c1345ab1d536aecbb379c3e2139ec298aa85e71c0d28d3b754ca8ee0bc5d