DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
MUNICIPALITY OF TUNGAWAN, ZAMBOANGA SIBUGAY Award a ₱16.9M contract to ZET CONSTRUCTIONMunicipalities
Transaction hash:
72d02c0e47b1774219064b2b5716d962ece8d4482e38fd780b5cfea757f7d9b8
Status:
Included and unchanged
Block:
#1,637 4,376 blocks after it
Position in block:
Transaction 6 of 12
Award day:
Dec 13, 2012 (13 yrs 11 mo ago)
Value:
₱16,938,178.33
Project:
Construction of Tungawan Public Market CUM Transport Terminal
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #1,637 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)The award does not say which budget line pays for it.Not published
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)MUNICIPALITY OF TUNGAWAN, ZAMBOANGA SIBUGAY awarded it to ZET CONSTRUCTION on 2012-12-13.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)No matching DPWH contract record (only DPWH contracts are listed with progress).Not published
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)No completion certificate published.Not published
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)COA's CY2024 audit of Tungawan gave a "qualified" opinion on its financial statements (not specific to this contract).Partly
1 of 8 documents found, 1 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 72d02c0e47…f7d9b8now …
- 2. Block Merkle root changedstored 8a4702dba7…15354enow …
- 3. Block #1637 hash changedstored a25e1bda2b…3c7504now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (4 steps)
How this one record is tied to the block's Merkle root, without needing the other 11 records. Each step hashes the current value together with the sibling shown.
- leaf 72d02c0e47b1774219064b2b5716d962ece8d4482e38fd780b5cfea757f7d9b8
- 01 R 73d6316721a767ba09376e253f45170e09021ff8c87a26087d3a25a428c47e01
- 02 L 73cc9cbbc3e7010ed1e25b2980d15479c5ea101301bee71dcca3557db02efebd
- 03 L 91e9c3037e0431c5f597b5103020109a9e88ff9cc2c82bd4bf15de522af06244
- 04 R 0dba70f26c1a7aab16474ca21ebe5065c26362f7e8dd5adb6c8ba019cd879741
- root 8a4702dba7d0d06d5e57520a387b39ba035c1b570be3b729d7d79ba7d715354e