DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
MUNICIPALITY OF MALINAO, ALBAY Award a ₱10.3M contract to 9LEAVES BUILDERS & SUPPLY CORP.Municipalities
Transaction hash:
7647e8953482566bf508f008bef91c7f9ed4602bed020bf33933c5a537ac7a04
Status:
Included and unchanged
Block:
#5,369 644 blocks after it
Position in block:
Transaction 21 of 54
Award day:
Dec 26, 2023 (2 yrs 10 mo ago)
Value:
₱10,254,151.53
Project:
Civil Workd
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #5,369 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)The award does not say which budget line pays for it.Not published
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)MUNICIPALITY OF MALINAO, ALBAY awarded it to 9LEAVES BUILDERS & SUPPLY CORP. on 2023-12-26.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)No matching DPWH contract record (only DPWH contracts are listed with progress).Not published
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)No completion certificate published.Not published
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)COA's CY2024 audit of Malinao gave a "modified" opinion on its financial statements (not specific to this contract).Partly
1 of 8 documents found, 1 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 7647e89534…ac7a04now …
- 2. Block Merkle root changedstored 52a6528877…c04b15now …
- 3. Block #5369 hash changedstored 3ddbd839fb…b29bednow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (6 steps)
How this one record is tied to the block's Merkle root, without needing the other 53 records. Each step hashes the current value together with the sibling shown.
- leaf 7647e8953482566bf508f008bef91c7f9ed4602bed020bf33933c5a537ac7a04
- 01 L 71383c8162caac86db1c53e7f8b7da68302bf5ca521b119376c6118c78e90add
- 02 R 44f1cbecaf12cd247a829273a6419a97c9cf2c32b741fdf883342000e7845fae
- 03 L 904796053a4f589d35430696fbe6289c062e6e9d6fa75ee92e3171c2b7ee144c
- 04 R 4b61506a01ddd332847a71c8708b7ca066a7c61d71b0328c32d10857889592de
- 05 L 80ea0bca85ce4f11d583160219f5c41b7447e154f36e6137e41644c874230ce2
- 06 R 521e037133d6f84aabb16997d20451b5456386782729e5bd1b7195752baf65f6
- root 52a6528877243b89f031d5d64501bf8e9c3ae9ab2f713f5a42610f101ec04b15