DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ALBAY 2ND DEO Award a ₱1.9M contract to GEMELLUS BUILDERS AND GENERAL SUPPLYNational agencies
Transaction hash:
7c8e49a8293ad0d21658ce995ccfd0e39c24ab8a137162d1113c14d656ea9700
Status:
Included and unchanged
Block:
#3,505 2,508 blocks after it
Position in block:
Transaction 89 of 181
Award day:
Aug 15, 2018 (8 yrs 2 mo ago)
Value:
₱1,930,497.37
Project:
LIP-Const. of MPB Brgy. 34, Oro Site, Leg. City
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,505 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2018 LP", i.e. the FY2018 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ALBAY 2ND DEO awarded it to GEMELLUS BUILDERS AND GENERAL SUPPLY on 2018-08-15.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 18FB0234: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2018-12-03). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 7c8e49a829…ea9700now …
- 2. Block Merkle root changedstored fa89079751…fab6e9now …
- 3. Block #3505 hash changedstored 83a4bb7233…79bb6bnow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (8 steps)
How this one record is tied to the block's Merkle root, without needing the other 180 records. Each step hashes the current value together with the sibling shown.
- leaf 7c8e49a8293ad0d21658ce995ccfd0e39c24ab8a137162d1113c14d656ea9700
- 01 L 7c291415c0e03cdd985724876993985a40f57e38fc8a19a9f21cd4a98b394662
- 02 R 482ec186dc7494d06a5001a6897ad50b356d0152765fea3d56773a74a867891a
- 03 R 31293a45a257c514fd29747fe9372866f06da8be96496eb95b85e81daa919889
- 04 L 01009240d336642ac36cc45fc2473c9a9c35ff098c66d4377a2123bc2fc70ef4
- 05 L 2104ad4cf1318ffa5f2e87acc413e9d1e2744d97e9a717f5cc51b58880b8c24b
- 06 R 8e23417be88f1b09e66c9603a494a481bd2180f6f07c1ead0f7d2e10f4fd5376
- 07 L 00c254801b3bafe2d8f1d1bfe091a27154f5382d101e18ad28b1e3a66f12c2cd
- 08 R 426a295ac1ea5b70b5deda788c136a5d56c825fb0bb4cc43bec5eebd158ddf1e
- root fa890797510f0fd8b98dbf1491bf5726e2c7f84c0d01fc61e7ae7fdb4ffab6e9