Skip to content
FY2026 GAA: ₱6.79T
PisoScan
DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction action

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTHERN SAMAR 1ST Award a ₱9.6M contract to WAR CONSTRUCTIONNational agencies

Transaction hash:
7dc5bb198db1e6cd6eb0e613824cfdbbccef5fd0e82150c315554343fcf6f4c0
Status:
Included and unchanged
Block:
#4,556 1,457 blocks after it
Position in block:
Transaction 112 of 217
Award day:
Sep 2, 2021 (5 yrs 2 mo ago)

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,556 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Regular Infra - GAA 2021 LP", i.e. the FY2021 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTHERN SAMAR 1ST awarded it to WAR CONSTRUCTION on 2021-09-02.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 21IH0082: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2022-08-02). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   7dc5bb198d…f6f4c0now      …
  2. 2. Block Merkle root changed
    stored   07cefc5ff9…ab2613now      …
  3. 3. Block #4556 hash changed
    stored   835dc73591…b16cd1now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (8 steps)

How this one record is tied to the block's Merkle root, without needing the other 216 records. Each step hashes the current value together with the sibling shown.

  1. leaf  7dc5bb198db1e6cd6eb0e613824cfdbbccef5fd0e82150c315554343fcf6f4c0
  2. 01 R 7eff99dbb17c24e9a45d2250dab6f15974eca67a1618f06bec3ca15662f263c3
  3. 02 R c5a6687b5678af5ac1210acf4af138a0528bacbf0c7ebb63ff29a64de5273870
  4. 03 R 2c7569f9c04c89b2ca28dae5e6c283cfd74f95afa215229a8fdf101fac8babc7
  5. 04 R 0b3510e25c5a28abf141bf1a8042e82d8db182a160503b9d0e3b8d94e776438c
  6. 05 L 1a40131df6d0b9512e6da5cfe96b3e313f01fab61be420e5a11c2d9159e4afbe
  7. 06 L 2a0279899f2a8759b7d56e417b06ad2aa1e4de2ab70883423ab27ae13438222b
  8. 07 L e5a7846669272962e5f7d14ebe136c6cf7b1553ebc2f41773d0712d3da445326
  9. 08 R fcad7bfb482b56f807317a65635ed4beb34fbb73a17baefc62c468762aee16fe
  10. root  07cefc5ff9b5c093d60934fe27faff0756eacb267544e57e61548c2bc0ab2613