DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BUTUAN CITY DEO Award a ₱8.2M contract to C'ZARLES CONSTRUCTION & SUPPLYNational agencies
Transaction hash:
7ee5fdebcf7e3e238458010e1898aadfda8fecac40bb56f1cc74eeaedd58367a
Status:
Included and unchanged
Block:
#2,856 3,157 blocks after it
Position in block:
Transaction 75 of 118
Award day:
Sep 21, 2016 (10 yrs 1 mo ago)
Value:
₱8,155,026.46
Project:
16ND0035
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #2,856 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Outside Infra - GAA 2016 DepED BEFF", i.e. the FY2016 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BUTUAN CITY DEO awarded it to C'ZARLES CONSTRUCTION & SUPPLY on 2016-09-21.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 16ND0035: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2017-05-12). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 7ee5fdebcf…58367anow …
- 2. Block Merkle root changedstored b5316dca88…92a6bcnow …
- 3. Block #2856 hash changedstored 43847ef492…92b2c5now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (7 steps)
How this one record is tied to the block's Merkle root, without needing the other 117 records. Each step hashes the current value together with the sibling shown.
- leaf 7ee5fdebcf7e3e238458010e1898aadfda8fecac40bb56f1cc74eeaedd58367a
- 01 L 7e772277c50bc9297910ca2e6a097579c5e699dc20aa7d922383d9363d7cfe4f
- 02 L 355ee8ebee8480aea8862286a1f8872f4ebd52aa76b0689b5d4842aaccd5225f
- 03 R ba207611c950c6968b35e64f9070fd6a41419fb2d6342fb11fb91fca5409ae58
- 04 L 18e1d23f1dd9a3bda7186dbd5d664fd6772b90c6b7f62efc467c0eb62fa5cef4
- 05 R b86d4a1b5ef5f103f08e3ad850800e0ee623a1b37829e67ff7afd9b7fc1d953e
- 06 R 03a77e0987a4e1700af02cd149f80dc8e2c81a29c81d96fbb5bb9941e2eeb4d7
- 07 L 646be0b789f6eac0a2db9b2da5968ab60d2f1766361fbdca2c9720bae1c9ff64
- root b5316dca88750ea8c9e2b012f8394120aa10d3f8ee3ffbd96147fffac192a6bc