APITransaction action
MUNICIPALITY OF LUBANG, OCCIDENTAL MINDORO Award a ₱428.8K contract to CITYSTAR CONSTRUCTIONMunicipalities
Transaction hash:
8f9089d7567ff92a4444d895baef53fc15c76d55ddea9d3894ea2d064a7da5e8
Status:
Included and unchanged
Block:
#5,094 919 blocks after it
Position in block:
Transaction 357 of 652
Award day:
Mar 15, 2023 (3 yrs 8 mo ago)
Value:
₱428,831.31
Project:
Vigo - Transmission Line
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #5,094 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)The award does not say which budget line pays for it.Not published
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)MUNICIPALITY OF LUBANG, OCCIDENTAL MINDORO awarded it to CITYSTAR CONSTRUCTION on 2023-03-15.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)No matching DPWH contract record (only DPWH contracts are listed with progress).Not published
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)No completion certificate published.Not published
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)COA's CY2024 audit of Lubang gave a "unmodified" opinion on its financial statements (not specific to this contract).Partly
1 of 8 documents found, 1 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 8f9089d756…7da5e8now …
- 2. Block Merkle root changedstored 266a5bf307…4e6efenow …
- 3. Block #5094 hash changedstored 0b162d390d…605ac6now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (10 steps)
How this one record is tied to the block's Merkle root, without needing the other 651 records. Each step hashes the current value together with the sibling shown.
- leaf 8f9089d7567ff92a4444d895baef53fc15c76d55ddea9d3894ea2d064a7da5e8
- 01 L 8f72b60cf78ef6f74c40119e39ee5f8cedc0886158281e9ec4fcabc43eaba6d2
- 02 R de7fb63fc61379c796dc80d7aec711b22d7ac22d96497e0f085362ca17e072be
- 03 L 2d90994c83e50a2c0ff0cf65473bec0fc8dc95736ad22fdba28362122f8c8072
- 04 R 94db8805c00dc5edb5ffe1d9e9428a38b174a0dec74926f00b0474c5a0a08af3
- 05 R c1c028d9003859aa109a5c52f7be1e36bcf389bba634b26098b43be0648e5bd4
- 06 L 6f50f480c2040c37ea46e460066d5a1c58120f52066c9521456551e4b23bde50
- 07 L fcea76bbd20abdce1bd83bbb4bc30087d6dd9b91c0d2a9c3c6fdaed16412a711
- 08 R d9cc781d0e20ac8d3414ca0185888aac0b2c6b5b9c92b44b63e6568069da4994
- 09 L 10b5dbed875c1566adc8cce2e74331cd824d1b033830a050978ffbdee7ba19a7
- 10 R 39d7feb5377f010cbb2c273938f282c3bb08e09e9cf6218b3029f267f2edcf62
- root 266a5bf307fbbdaca1c49474aebc68cc6605f37789c1d64ff3ffa8ac844e6efe