DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
NATIONAL TRANSMISSION CORPORATION - VISAYAS POWER CENTER Award a ₱729.4K contract to ET CONSTRUCTION AND GENERAL MERCHANDISENational agencies
Transaction hash:
9903a3c3950c8ecd762cbfd541ff5605e9a0e3c9a3b3eaf8778139a7e766c7fb
Status:
Included and unchanged
Block:
#174 5,839 blocks after it
Position in block:
Transaction 5 of 9
Award day:
Sep 17, 2007 (19 yrs 1 mo ago)
Value:
₱729,350.00
Project:
Construction of Lay-Down Area in Amlan Substation, Amlan, Negros Oriental
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #174 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)The award does not say which budget line pays for it.Not published
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)NATIONAL TRANSMISSION CORPORATION - VISAYAS POWER CENTER awarded it to ET CONSTRUCTION AND GENERAL MERCHANDISE on 2007-09-17.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)No matching DPWH contract record (only DPWH contracts are listed with progress).Not published
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)No completion certificate published.Not published
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
1 of 8 documents found, 0 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored 9903a3c395…66c7fbnow …
- 2. Block Merkle root changedstored af63a8707f…395085now …
- 3. Block #174 hash changedstored c3141be403…e3fa88now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (4 steps)
How this one record is tied to the block's Merkle root, without needing the other 8 records. Each step hashes the current value together with the sibling shown.
- leaf 9903a3c3950c8ecd762cbfd541ff5605e9a0e3c9a3b3eaf8778139a7e766c7fb
- 01 L 860b2b8eaaee89e26db4c2599dce7c424c000cac1b83e1426d17e4e058a7902e
- 02 R 1fcb22816b1c7d991ec371ab597ea21b142bce3f4fde32d24b0d9bd2e617495b
- 03 L f75d05e0c5e6a4e7878696b26d4b23305e6a6fb852c43f402aba0b504f9f5896
- 04 R 62f367a6d13fb6bf9d5219520477f0b93335ddf66c75eb9f1e058e57a628ac6d
- root af63a8707fa1469e142bc200981e84b905ca54f44f8cf4a5c349e7f94f395085