DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 5TH Award a ₱4.6M contract to LAHDETH CONSTRUCTION AND SUPPLYNational agencies
Transaction hash:
a047d4a51148f803b1bcfcbc1b56b6ef528ba5840fccbf65557bca21d2bc69d1
Status:
Included and unchanged
Block:
#3,982 2,031 blocks after it
Position in block:
Transaction 24 of 45
Award day:
Dec 31, 2019 (6 yrs 10 mo ago)
Value:
₱4,632,000.00
Project:
Concreting of Provincial Road from Brgy. Cabanban to Brgy. Pulang Daga. Balatan. Camarines Sur (Sta. 0+000.00 - Star 0+480.00)
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,982 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)The award does not say which budget line pays for it.Not published
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 5TH awarded it to LAHDETH CONSTRUCTION AND SUPPLY on 2019-12-31.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)No matching DPWH contract record (only DPWH contracts are listed with progress).Not published
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)No completion certificate published.Not published
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
1 of 8 documents found, 0 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored a047d4a511…bc69d1now …
- 2. Block Merkle root changedstored 40bf095424…ac5f19now …
- 3. Block #3982 hash changedstored 09e457fa04…4c256enow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (6 steps)
How this one record is tied to the block's Merkle root, without needing the other 44 records. Each step hashes the current value together with the sibling shown.
- leaf a047d4a51148f803b1bcfcbc1b56b6ef528ba5840fccbf65557bca21d2bc69d1
- 01 R a79a77396d324aaee3a6057c22b44ae426810b6670784b585336fb6388e471d0
- 02 R 1990b8dbbbecc21496d027d4be35b587b2dc51189d94971e75eca0142565e57d
- 03 R d94a213612bb14d2de974396fea0a157278c43009231f710c440105359c16ddb
- 04 L 28e7fec87e189bf2184f169a17afe1f8e61fca4e4a155b6f7438ccd19afb28a8
- 05 L 2d3496432f28b31dcc972a37be9f8b21548cc7e3de6f16610f61354a6184bbe1
- 06 R 588b2abc8d6266685bb9fe457e17fba59f04bbdc7d13b2bb1d72b42093e2f4e7
- root 40bf095424ab968f5ae3664f09d383c48f734c072936d8217fad46ebdeac5f19