DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED Award a ₱4.4M contract to STREAMLINE BUILDERS CORPORATIONNational agencies

Transaction hash:
a10d219eb7fbeebedb2c0721de8edb947673d92b0f6f579f966557a75239a8ec
Status:
Included and unchanged
Block:
#4,364 1,649 blocks after it
Position in block:
Transaction 198 of 316
Award day:
Feb 15, 2021 (5 yrs 8 mo ago)

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,364 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Regular Infra - GAA 2021 OO-1", i.e. the FY2021 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED awarded it to STREAMLINE BUILDERS CORPORATION on 2021-02-15.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 21DN0074: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2021-03-12). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   a10d219eb7…39a8ecnow      …
  2. 2. Block Merkle root changed
    stored   3b493f5f7e…5f7feanow      …
  3. 3. Block #4364 hash changed
    stored   0d3127cae0…cf28f0now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (9 steps)

How this one record is tied to the block's Merkle root, without needing the other 315 records. Each step hashes the current value together with the sibling shown.

  1. leaf  a10d219eb7fbeebedb2c0721de8edb947673d92b0f6f579f966557a75239a8ec
  2. 01 R a3a3f8225049bb792ce71cf816c842517676e0a41b1da12b7cf4909ff0b0521b
  3. 02 L 10f153e25dd0f86cb3247605ee15f147efe50d9586e1d57addb240d50b16dc73
  4. 03 L 3c8163442cc57e8c77c8d0be8049b1002a74b39189e71624c5b36d6fcfbfe8c0
  5. 04 R 6a56c8c6f6aca20ee3a8189e72557be15d260cfde52518a3af960ccb29b2d62b
  6. 05 R 6d5da68b41ad6f14985f77d398457c1d4bd788dcfb4b59511e634b39c36ab01f
  7. 06 R e8976d6375fb4a0b01e6ed6cd9393d77ff0def7e02d858fe042530533c624e91
  8. 07 L f861b598d2774192910af22de44de506f22a8afa4a0e259a50a522461a9bf6eb
  9. 08 L 1ad616549ae71bda19675d7bdd6237dcfde579b61ddd3f1ffb3eda9ad4f30267
  10. 09 R f28e4c03436f599e2b460393b75434b088c1ef3430a8fcbd032d6610a1c414ff
  11. root  3b493f5f7e60739d0fe98621a32bfa68115e560c980cb2ec12614163b55f7fea