DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BAGUIO CITY DEO Award a ₱7.1M contract to B-KILTEPAN BUILDERSNational agencies

Transaction hash:
a6bbbad61d7aaa043abb6b6a791b3c626d3982973848c6fd454e322bf99dd2c7
Status:
Included and unchanged
Block:
#5,156 857 blocks after it
Position in block:
Transaction 175 of 294
Award day:
May 17, 2023 (3 yrs 5 mo ago)

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #5,156 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Outside Infra - GAA 2023 DA FMR", i.e. the FY2023 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BAGUIO CITY DEO awarded it to B-KILTEPAN BUILDERS on 2023-05-17.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 23PD0068: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2023-11-26). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   a6bbbad61d…9dd2c7now      …
  2. 2. Block Merkle root changed
    stored   3ba10585fb…5ec860now      …
  3. 3. Block #5156 hash changed
    stored   4cc1078896…aafdb8now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (9 steps)

How this one record is tied to the block's Merkle root, without needing the other 293 records. Each step hashes the current value together with the sibling shown.

  1. leaf  a6bbbad61d7aaa043abb6b6a791b3c626d3982973848c6fd454e322bf99dd2c7
  2. 01 L a592839ea361cc8eabc3441ab38e39373b295fa11d3c53adf767d0685a943100
  3. 02 L 02bd86d21c2b90e418eedba6173f28a04cb27b2f2702a20fa34017a6c7a95f0b
  4. 03 L b1b53f863cdfb30f9cfc51f8344c19613dd0c0e5a4f745ea1ea73c63364e7da4
  5. 04 L 2db7feb3bdc76e12c7f705d4e7d71f1867e530ac76dd5ef23531b02a7f80599c
  6. 05 R b335d359efa8e7aed8e750265d2d957a78f0af0eca86e1c3c2398d39b243e2fa
  7. 06 L ce1d2a328a067f30a91fa78f8848a34f40c372994fa3a7c54aff4ff29e06230e
  8. 07 R 272a526cf0fcb540c25e8ed02c3e371b2dcd4c6689537b85e6c1ee212a61e5a4
  9. 08 L 291ef5aac29a4397b93f410d9d44ccd716adb1e81361bd823fda19662dee7517
  10. 09 R 870bc5f672f92d50557094c8564f68dcc0ea258fdc121582c5e1eab536523515
  11. root  3ba10585fbaaae505dba14aac7ce8856523732523224d61d5f949288435ec860