Skip to content
FY2026 GAA: ₱6.79T
PisoScan
DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction action

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LANAO DEL NORTE 2N Award a ₱4.0M contract to PAS BUILDERSNational agencies

Transaction hash:
b07e2134435c06e893e259aeb304114abadc4df48a59e2718d7ed96f2973dc2a
Status:
Included and unchanged
Block:
#4,099 1,914 blocks after it
Position in block:
Transaction 50 of 69
Award day:
May 7, 2020 (6 yrs 6 mo ago)

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #4,099 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Regular Infra - GAA 2020 CSSP", i.e. the FY2020 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LANAO DEL NORTE 2N awarded it to PAS BUILDERS on 2020-05-07.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 20KF0120: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2020-08-28). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   b07e213443…73dc2anow      …
  2. 2. Block Merkle root changed
    stored   eb58f8bfdb…ed5da4now      …
  3. 3. Block #4099 hash changed
    stored   3d291eb7ee…e73d20now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (7 steps)

How this one record is tied to the block's Merkle root, without needing the other 68 records. Each step hashes the current value together with the sibling shown.

  1. leaf  b07e2134435c06e893e259aeb304114abadc4df48a59e2718d7ed96f2973dc2a
  2. 01 R b2c437ed697add7ffc891fee0d7787abfa92c2e9f2ebffed19ebe7649bd325aa
  3. 02 L 960cd6c5b85b830344c82507eebb6ecbddf33272d43912a28afe1515113e6604
  4. 03 R 985311e3a097d5c145624f6fc90e5710ebf383560effa85b8836b76e7fa5b63c
  5. 04 R f2b128d06228001dafdf6a2019361762ac6febaf17d04dd52cde9b0c31a96bf9
  6. 05 L dd3a3e4eaab936fe28baecdb1c651f5140c480db511c00d54161eb290977d02e
  7. 06 L bc93f70f5774524a0fa455db1d299bc2055b8d624278185b1f1ed6f9388c4ef4
  8. 07 R 05150da5dacb201336ff226da326a1d32bc8347d765b503cf99a91ee35636fee
  9. root  eb58f8bfdb31b0d5ab06ed387bd04ad9801b0d70719a9247d7f1a3c19ded5da4