DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CEBU 1ST DEO Award a ₱2.8M contract to BANTAY CONSTRUCTIONNational agencies
Transaction hash:
b4c2e6b87ef28453560adcd3e74ace68945857a3b17018b7cde987a5bf756f7b
Status:
Included and unchanged
Block:
#3,488 2,525 blocks after it
Position in block:
Transaction 132 of 184
Award day:
Jul 26, 2018 (8 yrs 3 mo ago)
Value:
₱2,821,298.47
Project:
18HD0052
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,488 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2018 LP", i.e. the FY2018 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CEBU 1ST DEO awarded it to BANTAY CONSTRUCTION on 2018-07-26.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 18HD0052: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2018-09-15). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored b4c2e6b87e…756f7bnow …
- 2. Block Merkle root changedstored 297ec590ef…2c6321now …
- 3. Block #3488 hash changedstored f1a454f7a2…92b867now …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (8 steps)
How this one record is tied to the block's Merkle root, without needing the other 183 records. Each step hashes the current value together with the sibling shown.
- leaf b4c2e6b87ef28453560adcd3e74ace68945857a3b17018b7cde987a5bf756f7b
- 01 R b528774720c9954d22214c55e2169be9f4230bf114f78053aeacdc9b517fb318
- 02 R 3f370c4d9f3016de7e8890ca6fcb5dc15eeb0a35659c9ad609e20440336aea2d
- 03 L 11a6d95ea654491ce006e0c38190599e5265e841f3800d17a132d16ef5016454
- 04 R e7a17a529add041be0dce80a0609982ed8e353bbbc986ad86d7b5572f4ce8505
- 05 R 837d1ab8951652ecafe0e6fc1397cf4c80b73fba467ed1d2e6194be1e4282e05
- 06 R f50e43618eb0ee1dac57190c342f17a3fa2f2b043f7cb69b736b75a904ea65de
- 07 R a429c833e2842cdc8bfd6f3d0481bdc973b560583f53fbd012315789727ccbee
- 08 L 36f6fbc35ad5bb47f2a8d3ecb3fdc3b28686da9c89728bb5b34bbe625f81fed6
- root 297ec590efbb8c94315f35f4e77526021c30e4250dfd08a56bf2b181d72c6321