DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works
Transaction details
APITransaction action
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 5TH Award a ₱1.4M contract to E.S. BIHAG CONSTRUCTION & SUPPLYNational agencies
Transaction hash:
b55f232b4a7ea121515a71310942fff7b11814aea430e3aa1f0ce928280b81f9
Status:
Included and unchanged
Block:
#3,043 2,970 blocks after it
Position in block:
Transaction 194 of 283
Award day:
Apr 10, 2017 (9 yrs 7 mo ago)
Value:
₱1,410,595.00
Project:
Construction Projects
Full record:
Accountability
Bill Sec. 3 and 19Responsible agency:
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,043 signature valid Demo key, proves nothing about the governmentPublic key
Linked records: from budget to payment
Bill Sec. 5- 1. AppropriationGAA line item · Sec. 5(b)DPWH lists the funding source as "Regular Infra - GAA 2017 LFP", i.e. the FY2017 GAA. The exact UACS line is not given.Partly
- 2. Allotment releaseSARO / allotment · Sec. 5(c)(iii)Not published per project. DBM releases SAROs, but not linked to individual contracts.Not published
- 3. Cash allocationNotice of Cash Allocation · Sec. 5(c)(iv)Not published per project.Not published
- 4. Contract awardNotice of Award (PhilGEPS) · Sec. 5(d)DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 5TH awarded it to E.S. BIHAG CONSTRUCTION & SUPPLY on 2017-04-10.Found
- 5. Contract & progressContract / progress report (DPWH) · Sec. 5(d)DPWH contract 17FN0004: Completed, 100% physical progress.Found
- 6. PaymentDisbursement voucher · Sec. 5(c)(viii)Not published. No public source shows how much of this contract has been paid.Not published
- 7. CompletionCertificate of completion · Sec. 5(d)DPWH marks the contract "Completed" (end 2017-05-25). The certificate itself is not published.Partly
- 8. AuditCOA annual audit report · Sec. 5(e)(iii)No COA finding linked to this contract.Not published
2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.
Tamper test: try changing this record
DemoEdit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.
- 1. Record fingerprint changedstored b55f232b4a…0b81f9now …
- 2. Block Merkle root changedstored cdc86b44e8…142d7cnow …
- 3. Block #3043 hash changedstored 2651e34987…b4f71enow …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.
Merkle proof (9 steps)
How this one record is tied to the block's Merkle root, without needing the other 282 records. Each step hashes the current value together with the sibling shown.
- leaf b55f232b4a7ea121515a71310942fff7b11814aea430e3aa1f0ce928280b81f9
- 01 R b5b30b6a573e849cbb713ce601f9b1586af3acbbf0499314ce981581ea051b9c
- 02 L 3e921096f8cc1f7b362155b4281b91608edc7c6476fea0148b9dcfa052465a7a
- 03 R 4ad7a20c77334be20af5321180ff099dc85112c95550283fd5695203bb612f51
- 04 R b4aead32781e830459e49c36b39614faf53c9e799cbad642b14083df9abde8c5
- 05 R 0f2e264832db48499161bbab300f32f832e3c434d3091e8242b4fa00a5dfbc68
- 06 R 9d087585f582ebec05c824e8a68f2e5f3380545c331ff62df089edcc37ea4d60
- 07 L f07465dfa4a728d2499cb9f29b19ed9b87b88bca309c52193da7e4c0b6e2a47b
- 08 L 9b4c101bb813191132f7c3699a68fbf034f60427a43c12c34965283150f32d15
- 09 R f4dd47b54da8c607e271c98201e181bc6f4a16ecdff4abdf1069926a4930fecc
- root cdc86b44e8fe479d73f585c59cdb7bce9a839e607d089c54fa855f2960142d7c