FY2026 GAA: ₱6.79T
PisoScan
DemoFor public education only. These blocks are built by PisoScan from published PhilGEPS records to show how a budget ledger like CADENA would work. No government agency created or signed them, and this is not an official ledger. How it works

Transaction details

API
Transaction action

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAGAYAN DE ORO CIT Award a ₱3.3M contract to LANCE CONSTRUCTIONNational agencies

Transaction hash:
c7de9f091b3bf8d7a4021ff0e2b246f32e1b92495c83a16e0e7a8553eb91ea94
Status:
Included and unchanged
Block:
#3,260 2,753 blocks after it
Position in block:
Transaction 18 of 20
Award day:
Nov 30, 2017 (8 yrs 11 mo ago)

Accountability

Bill Sec. 3 and 19
Accountable officer:
Not stated in the source. PhilGEPS does not publish who certified the award.
Certification:
Not certified No agency signed this record. Under CADENA the accountable officer would sign it with their own key.
Demo signature:
Block #3,260 signature valid Demo key, proves nothing about the governmentPublic key

Linked records: from budget to payment

Bill Sec. 5
  1. 1. Appropriation
    GAA line item · Sec. 5(b)
    DPWH lists the funding source as "Regular Infra - GAA 2017 LFP", i.e. the FY2017 GAA. The exact UACS line is not given.
    Partly
  2. 2. Allotment release
    SARO / allotment · Sec. 5(c)(iii)
    Not published per project. DBM releases SAROs, but not linked to individual contracts.
    Not published
  3. 3. Cash allocation
    Notice of Cash Allocation · Sec. 5(c)(iv)
    Not published per project.
    Not published
  4. 4. Contract award
    Notice of Award (PhilGEPS) · Sec. 5(d)
    DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAGAYAN DE ORO CIT awarded it to LANCE CONSTRUCTION on 2017-11-30.
    Found
  5. 5. Contract & progress
    Contract / progress report (DPWH) · Sec. 5(d)
    DPWH contract 17KD0009: Completed, 100% physical progress.
    Found
  6. 6. Payment
    Disbursement voucher · Sec. 5(c)(viii)
    Not published. No public source shows how much of this contract has been paid.
    Not published
  7. 7. Completion
    Certificate of completion · Sec. 5(d)
    DPWH marks the contract "Completed" (end 2018-05-17). The certificate itself is not published.
    Partly
  8. 8. Audit
    COA annual audit report · Sec. 5(e)(iii)
    No COA finding linked to this contract.
    Not published

2 of 8 documents found, 2 partly. Under CADENA every step would be published within 7 working days and linked to this record.

Tamper test: try changing this record

Demo

Edit the amount as if someone quietly changed the record. Your browser re-hashes it and walks up the chain. Nothing is saved.

  1. 1. Record fingerprint changed
    stored   c7de9f091b…91ea94now      …
  2. 2. Block Merkle root changed
    stored   89cd9ac74f…15a48anow      …
  3. 3. Block #3260 hash changed
    stored   b40273ef44…1ac419now      …
Chain intact. The record matches its fingerprint, so the block and every block after it still line up.

Merkle proof (5 steps)

How this one record is tied to the block's Merkle root, without needing the other 19 records. Each step hashes the current value together with the sibling shown.

  1. leaf  c7de9f091b3bf8d7a4021ff0e2b246f32e1b92495c83a16e0e7a8553eb91ea94
  2. 01 R edaa918f8e3cbef7189f25bf82bffc19a3d2d00bb0aa740c2213b2b0d3a696ae
  3. 02 L 179ff2e6833ed9bcec6e48c0b43a48514a743376d0cc1f254d6052751066d921
  4. 03 R 8f84280203ac5dbdb735ce289872cf0fff9d09fbf422b4dad96f332d91cd1683
  5. 04 R fe5ec8e51c35364975a7fbe8615e65ae0d1fe97faa949f222ce9191567f9926d
  6. 05 L f5d25768f52eab1de8389eebaf79318a2347a348d2e52772623cac1823a2a390
  7. root  89cd9ac74f7c75294663c90428d4f4a50f6f6d410c0d69dee70f2bc8d815a48a